SMUDPV2 quarterly performance report IV for the period January through March 1987
Technical Report
·
OSTI ID:6387095
SMUDPV2 is a nominal 1 MW/sub AC/ photovoltaic (PV) power plant located adjacent to the Rancho Seco generating station, 30 miles southeast of Sacramento, California. The design and construction of PV2 was a joint effort between the Sacramento Municipal Utility District (SMUD) and the United States Department of Energy (DOE). It is the second phase of a multiphase PV power plant project with a planned generating capacity of 100 MW/sub AC/. SMUD's primary objective in this project is to install a PV power plant that will add economical energy generation capacity to their system. To this end, the data generated by the operation of PV2 will be used by SMUD to verify the value of PV to the rate payers of Sacramento, to assess the specific performance of the PV2 design, and to facilitate planning, design, and construction of future phases.
- Research Organization:
- Sacramento Municipal Utility District, CA (USA)
- DOE Contract Number:
- FC03-82CE30701; FC03-83CE11968
- OSTI ID:
- 6387095
- Report Number(s):
- SMUD-PV-2; ON: DE87011266
- Country of Publication:
- United States
- Language:
- English
Similar Records
SMUDPV2: Quarterly performance report No. 3 for the period October through December 1986
Plant performance for PV1 and PV2: SMUD (Sacramento Municipal Utility District) PV2, Final report 2, April 1986-March 1987
SMUD plans a [open quote]renewable[close quote] future. [Sacramento Municipal Utility District (SMUD)]
Technical Report
·
Wed Dec 31 23:00:00 EST 1986
·
OSTI ID:6526220
Plant performance for PV1 and PV2: SMUD (Sacramento Municipal Utility District) PV2, Final report 2, April 1986-March 1987
Technical Report
·
Mon Feb 29 23:00:00 EST 1988
·
OSTI ID:5323069
SMUD plans a [open quote]renewable[close quote] future. [Sacramento Municipal Utility District (SMUD)]
Journal Article
·
Wed Nov 30 23:00:00 EST 1994
· Fortnightly; (United States)
·
OSTI ID:6676981