Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Hanford No. 2 Integrating Transmission : Ashe-Hanford 500 KV Transmission Line Study Area 74-3.

Technical Report ·
OSTI ID:5779635
Proposed construction of a 17.8-mile 500-kV single-circuit line running from BPA's Ashe Substation Site near the Hanford No. 2 nuclear power plant site to the existing Hanford Switching Station. This facility would be located entirely within the Hanford Reservation of the Atomic Energy Commission north of the City of Richland in Benton County, Washington. Construction of the proposed transmission line would require a total right-of-way easement of approximately 612 acres through grassland. That area actually occupied by the tower footings would be removed from rangeland uses. Disturbance of game in the immediate vicintiy of the route will occur during construction as will some soil erosion primarily during and immediately after construction, siltation in nearby streams, distrubance of nearby residents from noise and dust during construction, and some degradation of AM reception immediately adjacent to the right-of-way. 10 figs.
Research Organization:
Bonneville Power Administration, Portland, OR (USA)
OSTI ID:
5779635
Report Number(s):
DES-74-25; ON: DE85014197