Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for San Juan Island Service : Decatur Land Line and East Lopez Island Substation Study Area 74-7.
Technical Report
·
OSTI ID:5558873
Proposed construction of a 1.7-mile 34.5-kV double-circuit transmission line crossing Decatur Island from east to west. The new line would replace 0.7 of a mile of an existing BPA 24.5-kV line and would then parallel and existing 24.5-kV line for a distance of 1.0 mile. The proposal also requires the construction of a new substation to be located on the eastern side of Lopez Island, Washington. The additional easement required for the proposed transmission line would remove about 1.1 acres of forestland from timber production diverting it to nonforest uses compatable with the transmission line right-of-way. Depending upon the actual site location the Lopez Island Substation could remove from 1 to 3.2 acres of forestland and 2 acres of pastureland from production. Disturbance of game in the immediate vicintiy of the transmission facilities will occur during construction, as will some soil erosion primarily during and immediately after construction, siltation in nearby streams, disturbance of nearby residents from noise and dust during construction, and some degradation of AM reception immediately adjacent to the right-of-way. 7 figs.
- Research Organization:
- Bonneville Power Administration, Portland, OR (USA)
- OSTI ID:
- 5558873
- Report Number(s):
- DES-74-26; ON: DE85014195
- Country of Publication:
- United States
- Language:
- English
Similar Records
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Raver-Tacoma 500-kV Transmission Line, Study Area 74-5.
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Hanford No. 2 Integrating Transmission : Ashe-Hanford 500 KV Transmission Line Study Area 74-3.
Final Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Maple Valley 500-KV Reinforcement, Study Area 75-14.
Technical Report
·
Fri Feb 15 00:00:00 EDT 1974
·
OSTI ID:5120459
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Hanford No. 2 Integrating Transmission : Ashe-Hanford 500 KV Transmission Line Study Area 74-3.
Technical Report
·
Fri Mar 08 00:00:00 EDT 1974
·
OSTI ID:5779635
Final Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Maple Valley 500-KV Reinforcement, Study Area 75-14.
Technical Report
·
Sun Nov 10 23:00:00 EST 1974
·
OSTI ID:5346117
Related Subjects
29 ENERGY PLANNING, POLICY, AND ECONOMY
290300 -- Energy Planning & Policy-- Environment
Health
& Safety
530200* -- Environmental-Social Aspects of Energy Technologies-- Assessment of Energy Technologies-- (-1989)
ANIMALS
BONNEVILLE POWER ADMINISTRATION
CLIMATES
CONSTRUCTION
ECOSYSTEMS
ENVIRONMENTAL IMPACTS
ENVIRONMENTAL QUALITY
Electric lines - Environmental aspects
FEDERAL REGION X
FORESTS
GEOLOGY
HYDROLOGY
INSTITUTIONAL FACTORS
LAND USE
NATIONAL ORGANIZATIONS
NORTH AMERICA
PACIFIC OCEAN
PLANTS
POWER TRANSMISSION LINES
PUGET SOUND
RANGELANDS
SEAS
SOCIO-ECONOMIC FACTORS
SURFACE WATERS
TERRESTRIAL ECOSYSTEMS
US DOE
US ORGANIZATIONS
USA
WASHINGTON
WATER QUALITY
290300 -- Energy Planning & Policy-- Environment
Health
& Safety
530200* -- Environmental-Social Aspects of Energy Technologies-- Assessment of Energy Technologies-- (-1989)
ANIMALS
BONNEVILLE POWER ADMINISTRATION
CLIMATES
CONSTRUCTION
ECOSYSTEMS
ENVIRONMENTAL IMPACTS
ENVIRONMENTAL QUALITY
Electric lines - Environmental aspects
FEDERAL REGION X
FORESTS
GEOLOGY
HYDROLOGY
INSTITUTIONAL FACTORS
LAND USE
NATIONAL ORGANIZATIONS
NORTH AMERICA
PACIFIC OCEAN
PLANTS
POWER TRANSMISSION LINES
PUGET SOUND
RANGELANDS
SEAS
SOCIO-ECONOMIC FACTORS
SURFACE WATERS
TERRESTRIAL ECOSYSTEMS
US DOE
US ORGANIZATIONS
USA
WASHINGTON
WATER QUALITY