Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Raver-Tacoma 500-kV Transmission Line, Study Area 74-5.
Technical Report
·
OSTI ID:5120459
Proposed construction of a 9.5-mile 500-kV double-circuit line connecting BPA's Raver and Covington Substations. The new line would replace 3.0 miles of existing BPA 230-kV lines and would then parallel an existing 500-kV line for 5.3 miles. Removal of 112 acres of forest, and diversion of that land to nonforest uses compatible with the transmission line right-of-way. Disturbance of game in the immediate vicinity of the route during construction, some soil erosion primarily during and immediately after construction, siltation in nearby streams, disturbance of nearby residents from noise and dust during construction, and some degradation of AM reception immediately adjacent to the right-of-way.
- Research Organization:
- USDOE Bonneville Power Administration, Portland, OR
- OSTI ID:
- 5120459
- Report Number(s):
- DES-74-12; ON: DE86001835
- Country of Publication:
- United States
- Language:
- English
Similar Records
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Hanford No. 2 Integrating Transmission : Ashe-Hanford 500 KV Transmission Line Study Area 74-3.
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for San Juan Island Service : Decatur Land Line and East Lopez Island Substation Study Area 74-7.
Final Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Maple Valley 500-KV Reinforcement, Study Area 75-14.
Technical Report
·
Fri Mar 08 00:00:00 EDT 1974
·
OSTI ID:5779635
Draft Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for San Juan Island Service : Decatur Land Line and East Lopez Island Substation Study Area 74-7.
Technical Report
·
Fri Mar 08 00:00:00 EDT 1974
·
OSTI ID:5558873
Final Supplement to the Environmental Statement Fiscal Year 1975 Proposed Program : Facility Location Evaluation for Maple Valley 500-KV Reinforcement, Study Area 75-14.
Technical Report
·
Sun Nov 10 23:00:00 EST 1974
·
OSTI ID:5346117
Related Subjects
20 FOSSIL-FUELED POWER PLANTS
200200* -- Fossil-Fueled Power Plants-- Waste Management
29 ENERGY PLANNING, POLICY, AND ECONOMY
290300 -- Energy Planning & Policy-- Environment
Health
& Safety
296000 -- Energy Planning & Policy-- Electric Power
530200 -- Environmental-Social Aspects of Energy Technologies-- Assessment of Energy Technologies-- (-1989)
BONNEVILLE POWER ADMINISTRATION
ELECTRIC UTILITIES
ENVIRONMENTAL IMPACTS
FEDERAL REGION X
MANAGEMENT
NATIONAL ORGANIZATIONS
NORTH AMERICA
Overhead electric lines - Environmental aspects
POWER TRANSMISSION LINES
PROGRAM MANAGEMENT
PUBLIC UTILITIES
SITE SELECTION
US DOE
US ORGANIZATIONS
USA
WASHINGTON
200200* -- Fossil-Fueled Power Plants-- Waste Management
29 ENERGY PLANNING, POLICY, AND ECONOMY
290300 -- Energy Planning & Policy-- Environment
Health
& Safety
296000 -- Energy Planning & Policy-- Electric Power
530200 -- Environmental-Social Aspects of Energy Technologies-- Assessment of Energy Technologies-- (-1989)
BONNEVILLE POWER ADMINISTRATION
ELECTRIC UTILITIES
ENVIRONMENTAL IMPACTS
FEDERAL REGION X
MANAGEMENT
NATIONAL ORGANIZATIONS
NORTH AMERICA
Overhead electric lines - Environmental aspects
POWER TRANSMISSION LINES
PROGRAM MANAGEMENT
PUBLIC UTILITIES
SITE SELECTION
US DOE
US ORGANIZATIONS
USA
WASHINGTON