Reasons for decision in the matter of Maritimes and Northeast Pipeline Management Ltd. application dated 24 February 1998 for approval of the plan, profile and book of reference respecting the detailed pipeline route from Goldboro, N.S. to St. Stephen, N.B.: MH-3-98
Technical Report
·
OSTI ID:321363
In December 1997, Maritimes and Northeast Pipeline Management Ltd. received approval to construct and operate a natural gas pipeline consisting of about 558 kilometers of 762-millimeter pipe to be located within a one-kilometer-wide corridor extending from Goldboro, Nova Scotia to the international border near St. Stephen, New Brunswick. This report covers the second stage of the pipeline approval process where the detailed route is determined. It presents the views of the pipeline company, various landowners and mineral rights holders objecting to the proposed detailed route, and the National Energy Board with regard to two issues: The best possible detailed route for the pipeline, and the most appropriate methods and timing of constructing the pipeline. Specific land/mineral rights owner cases including the nature of the objection, possible alternate routes, and the Board decision in each case are described.
- Research Organization:
- National Energy Board, Calgary, Alberta (Canada); Maritimes and Northeast Pipeline Management Ltd. (Canada)
- OSTI ID:
- 321363
- Report Number(s):
- MIC--99-01089/XAB; SSC-NE--22-1/1998-8E
- Country of Publication:
- United States
- Language:
- English
Similar Records
Reasons for decision in the matter of Maritimes and Northeast Pipeline Management Ltd., Point Tupper lateral facilities application, as amended, dated 14 August 1998: GH-4-98
Reasons for decision in the matter of Sable Offshore Energy Inc., application dated 9 June 1998 for approval of the plan, profile and book of reference respecting the detailed route of a subsea pipeline from the Thebaud platform to a landfall near Goldboro, Nova Scotia, and an onshore pipeline from the landfall point to the inlet of the gas processing plant located east of Goldboro, Nova Scotia: MH-4-98
Reasons for decision in the matter of TransCanada Pipelines Limited, application dated 29 April 1998, as amended, for 1999 facilities: GH-3-98
Technical Report
·
Thu Jul 01 00:00:00 EDT 1999
·
OSTI ID:362117
Reasons for decision in the matter of Sable Offshore Energy Inc., application dated 9 June 1998 for approval of the plan, profile and book of reference respecting the detailed route of a subsea pipeline from the Thebaud platform to a landfall near Goldboro, Nova Scotia, and an onshore pipeline from the landfall point to the inlet of the gas processing plant located east of Goldboro, Nova Scotia: MH-4-98
Technical Report
·
Wed Dec 30 23:00:00 EST 1998
·
OSTI ID:350340
Reasons for decision in the matter of TransCanada Pipelines Limited, application dated 29 April 1998, as amended, for 1999 facilities: GH-3-98
Technical Report
·
Wed Dec 30 23:00:00 EST 1998
·
OSTI ID:350342