Initial startup and operations of Yonggwang Units 3 and 4

Conference ·
OSTI ID:268043
;  [1];
  1. ABB Combustion Engineering Nuclear Systems, Windsor, CT (United States)
A significant milestone in the nuclear power industry was achieved in 1995, when Yonggwang (YGN) Units 3 and 4 were accepted into in commercial operation by Korea Electric Power Corporation (KEPCO). YGN Unit 3 was accepted into commercial operation on March 31, 1995, the original date established during project initiation. YGN Unit 4 was accepted into operation on January 1, 1996, 3 months ahead of schedule. Each YGN unit produces approximately 1,050 Mwe and supplies approximately ten percent of the total electric power demand in the Republic of Korea (ROK). The overall plant efficiency is approximately 37% which is at least 1% higher than most nuclear units. Since achieving commercial operation, YGN Unit 3 has operated at essentially full power which has resulted in an annual performance rate in excess of 85%. YGN Unit 3 is the first of six pressurized water reactors which are currently under design and construction in the ROK and serves as the reference design for the Korean Standard Nuclear Power Plant program. Both YGN Units 3 and 4 include a System 800 Nuclear Steam Supply System (NSSS). The NSSS is rated at 2,815 Mwth and is the ABB-CE standard design. The design includes numerous advanced design features which enhance plant safety, performance and operability. A well executed startup test program was successfully completed on both units prior to commercial operation. A summary of the YGN NSSS design features, the startup test program and selected test results demonstrating the performance of those features are presented in this paper.
OSTI ID:
268043
Report Number(s):
CONF-960306--; ISBN 0-7918-1226-X
Country of Publication:
United States
Language:
English

Similar Records

Yonggwang and Ulchin; A fully developed design, procurement, and construction model for U. S. application
Conference · Tue Dec 31 23:00:00 EST 1991 · Proceedings of the American Power Conference; (United States) · OSTI ID:7239404

Experience with human factors for an international client; Task analysis and operator surveys
Conference · Mon Dec 31 23:00:00 EST 1990 · Proceedings of the American Power Conference; (United States) · OSTI ID:6176437

Lessons learned in the successful construction and startup of Yonggwang Unit 3 Nuclear Power Plant
Conference · Thu Oct 31 23:00:00 EST 1996 · OSTI ID:389841