Repowering of lenenergo severnaya TETS-21 with lm6000 gas turbine. Export trade information
Technical Report
·
OSTI ID:220380
The study, conducted by Joseph Technology Corporation, was funded by the U.S. Trade and Development Agency. The report shows the results of a feasibility study done for the proposed repowering of the Severnaya TETS-21 power plant. The study includes various alternatives for the repowering, as well as an assessment of existing equipment and performance specifications needed to complete the project. The report is divided into the following sections: Executive Summary (1) Introduction; (2) Assessment of Existing Equipment; (3) Combined Cycle Evaluation; (4) Economic Analysis; (5) Impact of Environment. Appendices 1-4 follows the main body of the report. The study contains a second portion which is the Russian translation of the report.
- Research Organization:
- Joseph Technology Corp., Inc., Woodcliff Lake, NJ (United States)
- OSTI ID:
- 220380
- Report Number(s):
- PB--96-153630/XAB
- Country of Publication:
- United States
- Language:
- English
Similar Records
Yuzhno-sakhalin TET`s-1 modernization study. Volume 2. Export trade information
Mosenergo Ryazan Repowering Project (GRES-24). Feasibility study. Export trade information
Feasibility study for combustion-turbine repowering of North Bangkok Units 1, 2, and 3. Volume 2. Appendices. Export trade information
Technical Report
·
Mon May 01 00:00:00 EDT 1995
·
OSTI ID:118178
Mosenergo Ryazan Repowering Project (GRES-24). Feasibility study. Export trade information
Technical Report
·
Mon Feb 19 23:00:00 EST 1996
·
OSTI ID:229292
Feasibility study for combustion-turbine repowering of North Bangkok Units 1, 2, and 3. Volume 2. Appendices. Export trade information
Technical Report
·
Sun Sep 01 00:00:00 EDT 1991
·
OSTI ID:6909582