Title: Toms Creek Integrated Gasification Combined Cycle Demonstration Project. Final quarterly technical progress report for the period ending March 31, 1993

Technical Report ·
DOI:https://doi.org/10.2172/10177598· OSTI ID:10177598

This Quarterly Technical Progress Report for the period ending March 31, 1993 summarizes the work done to data by Tampella Power Corporation and Enviropower, Inc. on the integrated combined-cycle power plant project. Efforts were concentrated on the Toms Creek PDS (Preliminary Design and Studies). Tampella Power Corporation`s efforts were concentrated on the Toms Creek Preliminary Process Flow Diagram (PFD) and Piping and Instrument Diagrams (P&IDs). Tampella Power Corporation also prepared Heat and Material Balances (H&MBs) for different site-specific cases.

Research Organization:
Tampella Power Corp., Williamsport, PA (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
FC21-93MC29444
OSTI ID:
10177598
Report Number(s):
DOE/MC/29444-3403; ON: DE93019999
Resource Relation:
Other Information: PBD: 24 May 1993