skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Cryogenic Carbon Capture Development (Final Report)

Technical Report ·
DOI:https://doi.org/10.2172/1567014· OSTI ID:1567014

This project extends and leverages the work completed under funding from ARPA-E and other sources by exploring aspects of the Cryogenic Carbon Capture™ (CCC) process and issues discovered during those projects, but that were not within the scope or budget of previous projects or that became apparent during field tests. Our successful completion of the tasks outlined in this project has increased the reliability, efficiency, and scalability of the CCC process and we are better prepared for pilot-scale testing. The first phase of this project improved key areas of the process through iterative design and experiment, culminating with recommendations for improvements to the existing skid-scale system developed under non-federal funding. The second phase of this project implemented the improved unit operations into the Cryogenic Carbon Capture External Cooling Loop (CCC ECL™) skid and field tests the improved system at a coal-fired power plant. The specific areas of work in this project are: Budget Period 1: 1) Selection of the most energy-efficient drying system for ambient-pressure flue gas. Sustainable Energy Solutions, LLC (SES) has successfully demonstrated a dryer that removes bulk water using a low-temperature brine to remove about 99% of the water followed by a mol sieve 3A desiccant dryer to remove the remaining 1% water; 2) Selection and demonstration of efficient solution to fouling due to dissolved CO2. SES has tested several commercial heat exchangers that purport to be able to handle fouling issues similar to those experienced in the contact liquid chiller. Replicated tests using the CCC ECL™ skid and dimpled brazed plate heat exchangers demonstrate that quick throttling of refrigerant combined with a burst of clean gas mitigate the fouling caused by CO2 solubility in contact liquid with only minor increases in parasitic load. SES models indicate that parasitic load would increase by approximately 0.0125 GJ/tonne, an order of magnitude less than what was determined to be the maximum allowable additional parasitic load caused by this system; 3) Selection and demonstration of efficient and scalable solid–liquid separation system. The screw press technology met or exceeded the 70% solids loading benchmark during several test runs exceeding 24 hours on the CCC ECL™ skid. The average solids loading during the entire 50-hour run was 67%. The energy demand for this system is less than 0.1 GJe/tonne of CO2 processed; 4) Optimize design and demonstration of patented desublimating heat exchangers. We designed and built a hybrid spray tower that was tested over many hundreds of hours and a 50-hour continuous test run was completed capturing over 0.5 tonne CO2/day at >90% capture; (5) Plan for safe dilution of oxygen-depleted, cleaned flue-gas stream. The AERSCREEN simulator developed by the EPA modeled the dispersion of oxygen-depleted flue gas from the CCC process at a commercial plant. The results indicate that this plan effectively mitigates the flue gas hazards; (6) Simulation of and experimental work related to multi-pollutant capture. SES programmed an upgrade to its solid/vapor/liquid equilibrium (SVLE) algorithm. This enables simultaneous modeling of multiple pollutants (i.e., CO2, SOx, NOx, Hg, HCl). Budget Period 2; (7) Modify the CCC ECL™ skid for field testing and complete shakedown testing. The plans for modifying the CCC ECL™ skid were finalized and put into place. Shakedown testing of the updated CCC ECL™ skid occurred at SES using closed-loop mode (i.e., using a synthetic flue gas consisting of only N2 and CO2) and at the Hunter Power Plant using flue gas from the coal-fired boiler. Shakedown testing took longer than expected due to delays in receiving equipment and unexpected equipment performance in the field; (8) Operate the CCC ECL™ skid in the field. Longer testing of the CCC ECL™ skid occurred at the Hunter Power Plant. Multiple tests exceeding 35 hours were completed, with a total of over 600 hours of CO2 capture completed using flue gas at the Hunter Power Plant with an average CO2 capture rate of over 91% during those hours. Extensive notes and documentation were acquired informing improved methods for controls, startup, operation, and shut down; (9) Determine figures of merit and quantify process improvement. SES defined figures of merit for unit operation performance and overall CCC ECL™ process performance. All figures of merit were achieved or surpassed, except for 500 continuous hours of demonstration at the Hunter Power Plant; (10) Complete an Environmental Health and Safety Risk assessment by a third party. Tri-State completed an Environmental Health and Safety Risk assessment; (11) Update techno-economic analysis with third-party validation. The techno-economic analysis has been completed. It confirms the potential large reduction in energy and cost of the CCC process compared with leading alternatives and that the estimates and estimation techniques are reliable.

Research Organization:
Sustainable Energy Solutions, LLC., Orem, UT (United States)
Sponsoring Organization:
USDOE Office of Fossil Energy and Carbon Management (FECM)
DOE Contract Number:
FE0028697
OSTI ID:
1567014
Report Number(s):
DOE-SES-28697
Country of Publication:
United States
Language:
English

Similar Records

Recent Cryogenic Carbon Capture™ Field Test Results
Conference · Mon Apr 05 00:00:00 EDT 2021 · Social Science Research Network (SSRN) · OSTI ID:1567014

Cryogenic Carbon Capture™ (CCC) Status Report
Conference · Mon Apr 05 00:00:00 EDT 2021 · Social Science Research Network (SSRN) · OSTI ID:1567014

Pilot testing of a membrane system for postcombustion CO2 capture
Technical Report · Wed Sep 30 00:00:00 EDT 2015 · OSTI ID:1567014