Provisional process specifications for fabrication of KIT and KIIT target elements for K Reactor E-N load (PT-IP-561-C)
It is necessary to modify existing I&E fuel element components to produce the requested target elements by early April 1963. Normally, a minimum of eighteen weeks is required to produce components of a new design. Therefore, the finished target elements will not be of the optimum designed dimensions. The proposed minor deviations have been approved by Reactor Engineering for the demonstration load. It is anticipated that only these test quantities will be fabricated to these dimensions. These provisional process specifications are established on this basis and are subject to change as the fabrication techniques are developed.
- Research Organization:
- General Electric Co., Richland, WA (United States). Hanford Atomic Products Operation
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-76RL01830
- OSTI ID:
- 10148429
- Report Number(s):
- HW-77183; ON: DE94011284
- Resource Relation:
- Other Information: DN: Declassified; PBD: 20 Mar 1963
- Country of Publication:
- United States
- Language:
- English
Similar Records
Provisional specifications for prototypical lithium-aluminum target element 05T
I&E depleted uranium fuel element ruptures experienced under PT-IP-132-AC
A New Method for Low Cost Production of Titanium Alloys for Reducing Energy Consumption of Mechanical Systems
Technical Report
·
Mon Sep 02 00:00:00 EDT 1963
·
OSTI ID:10148429
I&E depleted uranium fuel element ruptures experienced under PT-IP-132-AC
Technical Report
·
Mon Dec 01 00:00:00 EST 1958
·
OSTI ID:10148429
A New Method for Low Cost Production of Titanium Alloys for Reducing Energy Consumption of Mechanical Systems
Technical Report
·
Mon Feb 29 00:00:00 EST 2016
·
OSTI ID:10148429