DIAGNOSIS, ANALYSIS, AND RESOLUTION OF THERMAL STABILITY ISSUES WITH HOM COUPLERS ON PROTOTYPE CEBAF SRF CAVITIES

Conference ·
OSTI ID:923384
During initial testing of the prototype cavities incorporated into the developmental cryomodule Renascence severe thermal stability issues were encountered during CW operation. Additional diagnostic instrumentation was added. This enabled identification of an unanticipated thermal impedance between the HOM coupler probe feedthrough assembly and the cavity beamtube. Subsequent detailed FE analysis successfully modeled the situation and indicated the need for alternate cooling path for the couplers on those cavities. HOM damping was measured to be adequate employing only two of the four HOM couplers. The two pickup probes on the couplers at the input power coupler side of each cavity were removed, the remaining HOM probe feedthroughs were heat stationed to two-phase helium supply piping, and a novel heat sink was added to station both the inner and outer conductors of the remaining HOM rf cables. The characterization measurements, analysis, modifications, and resulting performance are presented.
Research Organization:
Thomas Jefferson National Accelerator Facility, Newport News, VA
Sponsoring Organization:
USDOE - Office of Science (SC)
DOE Contract Number:
AC05-06OR23177
OSTI ID:
923384
Report Number(s):
JLAB-ACC-07-788; DOE/OR/23177-0309
Country of Publication:
United States
Language:
English

Similar Records

Testing of HOM coupler designs on a single cell niobium cavity
Conference · Sun May 01 00:00:00 EDT 2005 · OSTI ID:839999

Coaxial HOM Coupler designs tested on a single cell niobium cavity
Conference · Mon Aug 28 00:00:00 EDT 2006 · OSTI ID:890533

PERFORMANCE OF THE CEBAF PROTOTYPE CRYOMODULE RENASCENCE
Conference · Mon Feb 11 23:00:00 EST 2008 · OSTI ID:923385