Acceptance for Beneficial Use (ABU) Update for 241-AW-104 Waste Transfer Project
- CHG
In October of 2000 an Engineering Task Plan (ETP), RPP-6869, was drafted to define objectives, document requirements, and define organizational responsibilities for the purpose of design installation and turnover of the 241-AW-104 Pump Replacement Project The ETP included an Acceptance for Beneficial Use (ABU) checklist, which delineated all tasks necessary to turn the 241-AW-104 Replaced Transfer Pump over to Operations, Maintenance, and Plant Engineering Signature approval of the respective Engineering Data Transmittal (EDT 630501) signified agreement that the ABU checklist was all-inclusive. In January 2001 an additional EDT (EDT 624153) was drafted to define completed ABU items, provide corresponding supporting documentation, and status open items in need of completion. This supporting document is to serve two purposes: (1) update ABU checklist items completed since January 2001, and (2) define remaining ABU checklist items in need of completion.
- Research Organization:
- CHG (US)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM) (US)
- DOE Contract Number:
- AC27-99RL14047
- OSTI ID:
- 806802
- Report Number(s):
- RPP-7589, Rev.1; ECN-665966
- Country of Publication:
- United States
- Language:
- English
Similar Records
Acceptance for Beneficial Use (ABU) Update for 241-AW-104 Waste Transfer Project
241-SY-101 multi-functional instrument tree acceptance for beneficial use (ABU)
Partial Acceptance for Beneficial Use (ABU) for the Type 4 In Situ Vapor Sampler (ISVS) Carts
Technical Report
·
Tue Jan 16 23:00:00 EST 2001
·
OSTI ID:805936
241-SY-101 multi-functional instrument tree acceptance for beneficial use (ABU)
Technical Report
·
Mon Oct 02 00:00:00 EDT 1995
·
OSTI ID:409922
Partial Acceptance for Beneficial Use (ABU) for the Type 4 In Situ Vapor Sampler (ISVS) Carts
Technical Report
·
Fri May 19 00:00:00 EDT 2000
·
OSTI ID:803655