skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Engineering Analysis of Characterization Ramps and Platforms

Abstract

The calculations in Appendix A and B determine the adequacy of the ramps and platforms to accomplish two tasks: (1) Core sampling using the modifications imposed by the use of a FDNW foundation at PFP; and (2) Core sampling within the 200E and 200W Tank Farms without the imposed modifications. The calculations in this document determined that the ramps and platforms are adequate for use with core sampling equipment when sampling either tank 241-2-361 or within 200E or 200W Tank Farms. When sampling tank 241-2-361 the modifications made by ECN 651132 must be implemented. These modifications are the addition of diagonal cross bracing on both the lateral and longitudinal sides. Also, a 1 1/4 inch tie rod must connect both bases of each longitudinal side.

Authors:
Publication Date:
Research Org.:
NHC (US)
Sponsoring Org.:
ENVIRONMENTAL MANAGEMENT (US)
OSTI Identifier:
797685
Report Number(s):
HNF-4320, Rev.0
TRN: US0204904
DOE Contract Number:  
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 25 Aug 1999
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; SAMPLING; STORAGE FACILITIES; RADIOACTIVE WASTE STORAGE; SAMPLERS; MODIFICATIONS; DESIGN

Citation Formats

BOGER, R.M. Engineering Analysis of Characterization Ramps and Platforms. United States: N. p., 1999. Web. doi:10.2172/797685.
BOGER, R.M. Engineering Analysis of Characterization Ramps and Platforms. United States. doi:10.2172/797685.
BOGER, R.M. Wed . "Engineering Analysis of Characterization Ramps and Platforms". United States. doi:10.2172/797685. https://www.osti.gov/servlets/purl/797685.
@article{osti_797685,
title = {Engineering Analysis of Characterization Ramps and Platforms},
author = {BOGER, R.M.},
abstractNote = {The calculations in Appendix A and B determine the adequacy of the ramps and platforms to accomplish two tasks: (1) Core sampling using the modifications imposed by the use of a FDNW foundation at PFP; and (2) Core sampling within the 200E and 200W Tank Farms without the imposed modifications. The calculations in this document determined that the ramps and platforms are adequate for use with core sampling equipment when sampling either tank 241-2-361 or within 200E or 200W Tank Farms. When sampling tank 241-2-361 the modifications made by ECN 651132 must be implemented. These modifications are the addition of diagonal cross bracing on both the lateral and longitudinal sides. Also, a 1 1/4 inch tie rod must connect both bases of each longitudinal side.},
doi = {10.2172/797685},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1999},
month = {8}
}