Commissioning of the CEBAF Cryomodules

Conference ·
When complete, the Continuous Electron Beam Accelerator Facility will house a 4 GeV recirculating linear accelerator containing 42 1/4 cryomodules arrayed in two antiparallel linacs and an injector. Currently, over half of the cryomodules have been installed. Each cryomodule contains eight superconducting niobium 5-cell rf cavities that operate at 1.497 GHz [1]. A cryomodule must provide an energy gain of 20 MeV to the 200 mu-A beam [2]. The resultant dynamic heat load must be less than 45 W. The cavity parameters that are measured during the commissioning process include the external Q's of the cavity ports, the unloaded Q (Q{sub 0}) of the cavity as a function of accelerating gradient, and the maximum operating gradient of the cavity. The sensitivity of the resonant frequency to changes in pressure and gradient is also measured. Finally, the mechanical tuners are cycled and characterized. In all cases, the performance of CEBAF cryomodules has exceeded the design requirements. A portable test stand allows local control of the rf system and provides automated data acquisition. This paper describes the cryomodule commissioning hardware, software, and measurements.
Research Organization:
Thomas Jefferson National Accelerator Facility, Newport News, VA (US)
Sponsoring Organization:
USDOE Office of Energy Research (ER) (US)
DOE Contract Number:
AC05-84ER40150
OSTI ID:
787855
Report Number(s):
CEBAF-PR-93-042; DOE/ER/40150-1926
Country of Publication:
United States
Language:
English

Similar Records

CEBAF Cryomodule Commissioning in the South Linac
Conference · Fri Oct 01 00:00:00 EDT 1993 · OSTI ID:791942

COMMISSIONING AND OPERATION OF THE CEBAF 100 MV CRYOMODULES
Conference · Sun Jul 01 00:00:00 EDT 2012 · OSTI ID:1047737

Performance of the FEL cryomodules
Journal Article · Tue Sep 01 00:00:00 EDT 1998 · OSTI ID:754513