Trojan Decommissioning Project Cost Performance

Conference ·
OSTI ID:785829
The Trojan nuclear plant (Trojan) was an 1160-MW(electric) four-loop pressurized water reactor located in Rainier, Oregon. The plant was permanently shut down in 1993 after {approx}17 yr of commercial operation. The early plant closure was an economic decision. The key factors in the closure analysis were escalation of inspection and repair costs associated with steam generator tube cracking and the projected availability of inexpensive replacement power in the Pacific Northwest region of the United States. Since the plant closure, Portland General Electric (PGE) has been actively engaged in decommissioning. The Trojan Decommissioning Project currently has a forecast at completion of $429.7 million (all costs are in millions of 1997 dollars, unless otherwise noted). The cost performance of the Trojan Decommissioning Project to date is addressed, as well as the tools that are in place to provide cost control through completion of decommissioning.
Research Organization:
Portland General Electric Company, Rainier, OR (US)
Sponsoring Organization:
none (US)
OSTI ID:
785829
Report Number(s):
none; ISSN 0003-018X; CODEN TANSAO; ISSN 0003-018X; CODEN TANSAO
Country of Publication:
United States
Language:
English

Similar Records

Shippingport: A relevant decommissioning project
Conference · Thu Dec 31 23:00:00 EST 1987 · OSTI ID:5122995

The Trojan Large Component Removal Project
Conference · Sun Sep 01 00:00:00 EDT 1996 · OSTI ID:277796

Oregon utility: N-shutdown may force electricity cutbacks. [Portland General Electric]
Journal Article · Sun Dec 23 23:00:00 EST 1979 · Energy User News; (United States) · OSTI ID:5620145