BI-GAS Pilot Plant. Quarterly technical progress report, October 21-December 31, 1982
Technical Report
·
OSTI ID:6946084
Work on deactivation of the BI-GAS Pilot Plant continued through mid-November 1982, at which time approximately 95 percent of the scheduled reversible mothballing activities were complete. On November 15, instructions were received from the Department of Energy to cease mothballing, pending further notification on probably reactivation of the facilities. Appropriate program planning was initiated to develop future test objectives. The status of the BI-GAS Pilot Plant remained on hold during December 1982 pending notification on reactivation of the facilities. Reversible mothballing held at approximately 95 percent completion. 3 figures.
- Research Organization:
- Stearns-Roger, Inc., Denver, CO (USA)
- DOE Contract Number:
- AC21-80ET14705
- OSTI ID:
- 6946084
- Report Number(s):
- DOE/ET/14705-57; ON: DE84003983
- Country of Publication:
- United States
- Language:
- English
Similar Records
BI-GAS pilot plant. Quarterly technical progress report, 1 July 1982-30 September 1982
BI-GAS Illinois coal gasification program. Final technical report, September 1982-September 1983
BI-GAS Pilot-Plant operation. Quarterly technical progress report, January 1-March 31, 1983
Technical Report
·
Thu Dec 31 23:00:00 EST 1981
·
OSTI ID:7025158
BI-GAS Illinois coal gasification program. Final technical report, September 1982-September 1983
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:5525638
BI-GAS Pilot-Plant operation. Quarterly technical progress report, January 1-March 31, 1983
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:6710858