KILnGAS RAM I (Reliability, Availability, and Maintainability) test report
Technical Report
·
OSTI ID:6917979
This report presents a summary of findings and results of the first phase of the KILnGAS Reliability, Availability, and Maintainability (RAM) test program. The first phase, known as RAM I, was completed in April 1986. The second step, RAM IIA, is scheduled for completion by the end of 1986; and the third step, RAM IIB, is planned to be completed by the third quarter of 1987. The RAM test program is being conducted by Allis-Chalmers Coal Gas Corporation using the KILnGAS Commercial Module (KCM). The KCM is a 600-ton-per-day coal gasification plant located in East Alton, Illinois, on the site of the Illinois Power Company's Wood River Generating Station. The KCM is designed to provide approximately 400 million Btu per hour of clean low-Btu gaseous fuel to a corner-fired 50 megawatt steam boiler. Design and construction of the plant was started in 1980. Commissioning and startup tests were initiated in mid-1983, and performance tests, which verified the technical feasibility of the KILnGAS process, using Illinois No. 6 coal, were concluded in December 1984. The RAM I program began on January 1, 1985. The overall goal of the RAM I program was to improve plant performance beyond that experienced during the 1984 demonstration run. This included modifications of the plant, principally to the ash discharge system, to permit operation at increased carbon conversion levels. Subsequent test results were generally positive. 19 figs., 6 tabs.
- Research Organization:
- Allis-Chalmers Coal Gas Corp., Milwaukee, WI (USA)
- DOE Contract Number:
- FC21-85MC22146
- OSTI ID:
- 6917979
- Report Number(s):
- DOE/MC/22146-2236; ON: DE87001042
- Country of Publication:
- United States
- Language:
- English
Similar Records
KILnGAS RAM (Reliability, Availability, and Maintainability) IIA summary test report
KILnGAS RAM IIB final technical report: Topical report
Second phase of Kilngas RAM program to be completed in December 86
Technical Report
·
Tue Mar 31 23:00:00 EST 1987
·
OSTI ID:6208268
KILnGAS RAM IIB final technical report: Topical report
Technical Report
·
Thu Mar 31 23:00:00 EST 1988
·
OSTI ID:6983691
Second phase of Kilngas RAM program to be completed in December 86
Journal Article
·
Sun Nov 30 23:00:00 EST 1986
· Pace Synth. Fuels Rep.; (United States)
·
OSTI ID:6223763
Related Subjects
01 COAL, LIGNITE, AND PEAT
010404* -- Coal
Lignite
& Peat-- Gasification
AVAILABILITY
COAL GASIFICATION
DATA
EXPERIMENTAL DATA
FEDERAL REGION V
FLUIDS
FUEL GAS
FUELS
GAS FUELS
GASES
GASIFICATION
ILLINOIS
INFORMATION
KILNGAS PROCESS
LOW BTU GAS
MAINTENANCE
MODIFICATIONS
NORTH AMERICA
NUMERICAL DATA
PERFORMANCE TESTING
PRODUCTION
RELIABILITY
TESTING
THERMOCHEMICAL PROCESSES
USA
YIELDS
010404* -- Coal
Lignite
& Peat-- Gasification
AVAILABILITY
COAL GASIFICATION
DATA
EXPERIMENTAL DATA
FEDERAL REGION V
FLUIDS
FUEL GAS
FUELS
GAS FUELS
GASES
GASIFICATION
ILLINOIS
INFORMATION
KILNGAS PROCESS
LOW BTU GAS
MAINTENANCE
MODIFICATIONS
NORTH AMERICA
NUMERICAL DATA
PERFORMANCE TESTING
PRODUCTION
RELIABILITY
TESTING
THERMOCHEMICAL PROCESSES
USA
YIELDS