Waste Isolation Pilot Plant contact-handled transuranic waste preoperational checkout: Final report
Technical Report
·
OSTI ID:6725718
This report documents the results of the WIPP CH TRU Preoperational Checkout which was completed between June 8 and June 14, 1988 during which period, a total of 10 TRUPACT shipping containers were processed from site receipt through emplacement of the simulated waste packages in the underground storage area. Since the design of WIPP includes provisions to unload an internally contaminated TRUPACT, in the controlled environment of the Overpack and Repair Room, one TRUPACT was partially processed through this sequence of operations to verify this portion of the waste handling process as part of the checkout. The successful completion of the CH TRU Preoperational Checkout confirmed the acceptability of WIPP operating procedures, personnel, equipment, and techniques. Extrapolation of time-line data using a computer simulation model of the waste handling process has confirmed that WIPP operations can achieve the design throughput capability of 500,000 ft/sup 3//year, if required, using two waste handling shifts. The single shift throughput capability of 273,000 ft/sup 3//year exceeds the anticipated operating receival rate of about 230,000 ft/sup 3//year. At the 230,000 ft/sup 3//year rate, the combined CH TRU annual operator dose and the average individual dose (based on minimum crew size) is projected to be 13.7 rem and 0.7 rem, respectively. 6 refs., 27 figs., 3 tabs.
- Research Organization:
- Westinghouse Electric Corp., Carlsbad, NM (USA). Waste Isolation Div.
- DOE Contract Number:
- AC04-86AL31950
- OSTI ID:
- 6725718
- Report Number(s):
- DOE/WIPP-88-012; ON: DE89002765
- Country of Publication:
- United States
- Language:
- English
Similar Records
Waste Isolation Pilot Plant CH TRU preoperational checkout plan
TRU waste shipment dry run preoperational checkout plan
Waste Isolation Pilot Plant RH TRU waste preoperational checkout: Final report
Technical Report
·
Tue Feb 09 23:00:00 EST 1988
·
OSTI ID:6725746
TRU waste shipment dry run preoperational checkout plan
Technical Report
·
Thu Aug 01 00:00:00 EDT 1991
·
OSTI ID:6216889
Waste Isolation Pilot Plant RH TRU waste preoperational checkout: Final report
Technical Report
·
Wed Jun 01 00:00:00 EDT 1988
·
OSTI ID:6709254
Related Subjects
052002* -- Nuclear Fuels-- Waste Disposal & Storage
053000 -- Nuclear Fuels-- Environmental Aspects
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES
ALPHA-BEARING WASTES
CONTAINERS
DEMONSTRATION PROGRAMS
DOCUMENT TYPES
EVALUATION
FUNCTIONAL MODELS
MANAGEMENT
MATERIALS
NATIONAL ORGANIZATIONS
NUCLEAR FACILITIES
OPERATION
PILOT PLANTS
PROGRESS REPORT
RADIOACTIVE MATERIALS
RADIOACTIVE WASTE FACILITIES
RADIOACTIVE WASTES
UNDERGROUND DISPOSAL
UNDERGROUND FACILITIES
US DOE
US ORGANIZATIONS
WASTE DISPOSAL
WASTE MANAGEMENT
WASTE RETRIEVAL
WASTES
WIPP
053000 -- Nuclear Fuels-- Environmental Aspects
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES
ALPHA-BEARING WASTES
CONTAINERS
DEMONSTRATION PROGRAMS
DOCUMENT TYPES
EVALUATION
FUNCTIONAL MODELS
MANAGEMENT
MATERIALS
NATIONAL ORGANIZATIONS
NUCLEAR FACILITIES
OPERATION
PILOT PLANTS
PROGRESS REPORT
RADIOACTIVE MATERIALS
RADIOACTIVE WASTE FACILITIES
RADIOACTIVE WASTES
UNDERGROUND DISPOSAL
UNDERGROUND FACILITIES
US DOE
US ORGANIZATIONS
WASTE DISPOSAL
WASTE MANAGEMENT
WASTE RETRIEVAL
WASTES
WIPP