Plant standardization: the French experience
Conference
·
· Trans. Am. Nucl. Soc.; (United States)
OSTI ID:6582778
In December 1985, 54 pressurized water reactor (PWR) units have been ordered and among them, 37, including five 1300-MW units, were in operation, the two oldest ones having been commissioned in 1977. In 1985, these plants generated 213 TWh with a capacity factor of approx. 83% (approx. 65% of the electricity generated in France). These performances result from favorable factors, one of these being the standardization policy of the French utility Electricite de France (EdF) for the components, design, and operation of the plants. Acting as architect/engineer, project manager, owner, and operator of its plants, EdF chose single nuclear steam supply system (NSSS) and turbo-generator suppliers for its nuclear plants. Also recall that EdF had already experienced a standardization policy since 1948 for its coal and oil-fired power stations. Standardization was a condition necessary for the success of the French nuclear program when four to six PWR units were ordered every year between 1974 and 1980. The goal was to concentrate on the first units' extensive design and tests in order to shorten delivery times, improve industrial efficiency, and reduce costs. The standardization policy applied to the implementation of the French nuclear program remains the major pillar of its success. The construction costs, construction time, and overall availability of a very large nuclear plant park are certainly the best illustrations of this view.
- Research Organization:
- Electricite de France, Paris
- OSTI ID:
- 6582778
- Report Number(s):
- CONF-860610-
- Conference Information:
- Journal Name: Trans. Am. Nucl. Soc.; (United States) Journal Volume: 52
- Country of Publication:
- United States
- Language:
- English
Similar Records
The N4 1450-MW(electric) series: The new generation of French PWRs
France stakes its energy future on nuclear power
Plutonium reload experience and perspective in French pressurized water reactors
Journal Article
·
Mon Dec 30 23:00:00 EST 1996
· Transactions of the American Nuclear Society
·
OSTI ID:426283
France stakes its energy future on nuclear power
Journal Article
·
Fri Dec 31 23:00:00 EST 1976
· Electr. Light Power (Boston); (United States)
·
OSTI ID:7320236
Plutonium reload experience and perspective in French pressurized water reactors
Conference
·
Sat Dec 31 23:00:00 EST 1988
· Transactions of the American Nuclear Society; (USA)
·
OSTI ID:6769695
Related Subjects
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS
210800* -- Nuclear Power Plants-- Economics
CONSTRUCTION
DESIGN
ENERGY SYSTEMS
EUROPE
FRANCE
OPERATION
PERFORMANCE
PLANNING
PWR TYPE REACTORS
REACTOR OPERATION
REACTORS
STANDARDIZATION
STEAM SYSTEMS
WATER COOLED REACTORS
WATER MODERATED REACTORS
WESTERN EUROPE
210800* -- Nuclear Power Plants-- Economics
CONSTRUCTION
DESIGN
ENERGY SYSTEMS
EUROPE
FRANCE
OPERATION
PERFORMANCE
PLANNING
PWR TYPE REACTORS
REACTOR OPERATION
REACTORS
STANDARDIZATION
STEAM SYSTEMS
WATER COOLED REACTORS
WATER MODERATED REACTORS
WESTERN EUROPE