The guying system is the feature that most distinguishes the Lena guyed tower from a conventional fixed-bottom platform. Special equipment and procedures were required to handle and place 6-foot diameter anchor piles, 200-ton clump weights, and both 5-inch and 5 3/8-inch diameter guyline segments in 1000 feet of water. Many procedural alternatives were evaluated for each discrete step of the guying system installation. Various equipment concepts were studied for each alternative. The cost of each option was determined and the compatibility with all other options was assessed. The most reliable and cost-effective alternatives were selected for the final installation plan, which will be discussed in this paper. The effectiveness of the installation planning was verified by the success of the Lena installation. The unique equipment proved to be reliable and the efficiency of the newly developed offshore construction methods was demonstrated.

Research Organization:
Exxon Co.
OSTI ID:
6418077
Report Number(s):
CONF-8405208-
Journal Information:
Proc., Annu. Offshore Technol. Conf.; (United States), Journal Name: Proc., Annu. Offshore Technol. Conf.; (United States) Vol. 1; ISSN OSTCB
Country of Publication:
United States
Language:
English

Similar Records

Dynamically positioned Derrick Barge and position measuring equipment for Lena guyed tower installation
Conference · Tue May 01 00:00:00 EDT 1984 · Proc., Annu. Offshore Technol. Conf.; (United States) · OSTI ID:6162265

Jacket, deck, and pipeline installation Lena guyed tower
Conference · Tue May 01 00:00:00 EDT 1984 · Proc., Annu. Offshore Technol. Conf.; (United States) · OSTI ID:6371484

Design of the Lena guyed tower
Conference · Tue May 01 00:00:00 EDT 1984 · Proc., Annu. Offshore Technol. Conf.; (United States) · OSTI ID:6454219