10 MWe Solar Thermal Central Receiver Pilot Plant total capital cost

Technical Report ·
DOI:https://doi.org/10.2172/6008642· OSTI ID:6008642

A detailed breakdown of the capital cost of the 10 MWe Solar Thermal Central Receiver Pilot Plant located near Barstow, California is presented. The total capital requirements of the pilot plant are given in four cost breakdown structures: (1) project costs (research and development, design, factory, construction, and start-up); (2) plant system costs (land, structures and improvements, collector system, receiver system, thermal transport system, thermal storage system, turbine-generator plant system, electrical plant system, miscellaneous plant equipment, and plant level); (3) elements of work costs (sitework/earthwork, concrete work, metal work, architectural work, process equipment, piping and electrical work); and (4) recurring and non-recurring costs. For all four structures, the total capital cost is the same ($141,200,000); however, the allocation of costs within each structure is different. These cost breakdown structures have been correlated to show the interaction and the assignment of costs for specific areas.

Research Organization:
Sandia National Labs., Livermore, CA (USA)
DOE Contract Number:
AC04-76DR00789
OSTI ID:
6008642
Report Number(s):
SAND83-8019; ON: DE85009113
Country of Publication:
United States
Language:
English