Pipeline gas from coal-hydrogenation (IGT hydrogasification process). Project 9000 monthly status report, January 1--January 31, 1978

Technical Report ·
DOI:https://doi.org/10.2172/5222839· OSTI ID:5222839
Two tests were conducted during January. Test 68 was terminated after 20 hours of char feed to the reactor due to a leak in a reactor manway. Test 69 was started after conducting a turnaround. Stable conditions were established in the reactor at a char feed rate exceeding 2 tons/hr, when a liquid nitrogen shortage, caused by a severe winter storm, forced us to terminate the test. Further information was supplied to Procon, Inc., to aid its staff in their design of a commercial/demonstration HYGAS plant. Additional test work was done on the lift-pot, lift-line feeder device. Results of a preliminary engineering study on the design of a hot-liquid quench system for the HYGAS plant are presented.
Research Organization:
Institute of Gas Technology, Chicago, Ill. (USA)
OSTI ID:
5222839
Report Number(s):
FE-2434-26
Country of Publication:
United States
Language:
English