Modeling brine inflow to Room Q: A numerical investigation of flow mechanisms
- INTERA Inc., Albuquerque, NM (United States)
- Sandia National Labs., Albuquerque, NM (United States). Geohydrology Dept.
A hydrologic modeling study was performed to gain insight into the flow mechanisms around Room Q. A summary of hydrologic and structural data and of predictive fluid flow models from Room Q are provided. Six years of measured data are available from the time of excavation. No brine accumulation in Room Q was measured in the first two years following excavation. However, there is considerable uncertainty associated with this early-time data due to inadequate sealing of the room. Brine may have been lost to evaporation or it may have flowed into newly created disturbed rock zone (DRZ) porosity resulting from excavation. Non-zero brine accumulation rates were measured from 2--5 years, but brine accumulation within the room dropped to zero after 5.5 years. A conceptual model for brine inflow to Room Q was developed which assumes far-field Darcy flow combined with an increasing DRZ pore volume. Numerical simulations employed TOUGH28W and used predictive DRZ porosity increase with time from SPECTROM-32 rock deformation simulations. Simulated brine inflow showed good agreement with measured brine accumulation rates for the first five years. Two important conclusions were drawn from the simulation results: (1) early-time brine inflow to the room can be reduced to zero if the DRZ pore volume increases with time, and (2) brine accumulation (inflow) rates from 2 to 5 years suggest a far-field permeability of 5 {times} 10{sup {minus}22} m{sup 2} with a bulk rock compressibility of 5.4 {times} 10{sup {minus}12} Pa{sup {minus}1}.
- Research Organization:
- Sandia National Labs., Albuquerque, NM (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC04-94AL85000
- OSTI ID:
- 481483
- Report Number(s):
- SAND--96-0561; ON: DE97007440
- Country of Publication:
- United States
- Language:
- English
Similar Records
Test plan: Brine inflow and related tests in the brine inflow room (Room Q) of the Waste Isolation Pilot Plant (WIPP)
Test plan: Brine inflow and related tests in the brine inflow room (Room Q) of the Waste Isolation Pilot Plant (WIPP)
Implementation of initial tests in the Brine Inflow Room (Room Q) of the Waste Isolation Pilot Plant
Technical Report
·
Wed Feb 28 23:00:00 EST 1990
·
OSTI ID:10146669
Test plan: Brine inflow and related tests in the brine inflow room (Room Q) of the Waste Isolation Pilot Plant (WIPP)
Technical Report
·
Wed Feb 28 23:00:00 EST 1990
·
OSTI ID:6863201
Implementation of initial tests in the Brine Inflow Room (Room Q) of the Waste Isolation Pilot Plant
Technical Report
·
Tue May 01 00:00:00 EDT 1990
·
OSTI ID:6910712