Non-active and active commissioning of the thermal oxide reprocessing plant (Thorp)

Conference ·
OSTI ID:476588

British Nuclear Fuels plc (BNFL) completed construction of its Thermal Oxide Reprocessing Plant (Thorp) at the Sellafield site, Cumbria, UK in 1992; approximately 18 years after the start of conceptual design and development work. During the latter period of construction to the present time various commissioning activities have been carried out. These activities have presented the plant with an increasing challenge, ranging from a variety of non-active tests to commissioning with active fuel. All aspects of the plant have been tested together with associated plants which treat wastes and effluents arising from Thorp.

OSTI ID:
476588
Report Number(s):
CONF-960804--Vol.3
Country of Publication:
United States
Language:
English

Similar Records

BNFL receives approval for THORP testing
Journal Article · Wed Sep 01 00:00:00 EDT 1993 · NUEXCO. Monthly Report to the Nuclear Industry; (United States) · OSTI ID:6996494

BNFL experience in the design and operation of spent fuel storage facilities
Conference · Thu Dec 30 23:00:00 EST 1993 · OSTI ID:100798

Public relations activities in BNFL
Journal Article · Thu Dec 30 23:00:00 EST 1993 · Transactions of the American Nuclear Society · OSTI ID:107208