PACKAGE POWER REACTOR NO. 1 STEAM CYCLE CALCULATIONS
Technical Report
·
OSTI ID:4353827
A study was made to determine the best steam cycle arrangement and reactor power requirement for a package power reactor system to supply a remote army station requiring 1OOO kw of electricity and 250 boiler horsepower (7.55 x 10/sup 6/ Btu/hr) of steam heating load. It was assumed that gross electric power requirement would be 1300 kw of electricity. (auth)
- Research Organization:
- Oak Ridge National Lab., Tenn.
- DOE Contract Number:
- W-7405-ENG-26
- NSA Number:
- NSA-12-007463
- OSTI ID:
- 4353827
- Report Number(s):
- CF-53-3-213
- Country of Publication:
- United States
- Language:
- English
Similar Records
Design Analysis of a Prepackaged Nuclear Power Plant (1000 eKW). Volume II. Reactor Design Analysis
DESIGN ANALYSIS OF A PREPACKAGED NUCLEAR POWER PLANT (1000 eKW). VOLUME I. PRIMARY AND SECONDARY SYSTEM DESIGN
Retrofit utility power plant to combined cycle operation
Technical Report
·
Sat Jan 31 23:00:00 EST 1959
·
OSTI ID:1129041
DESIGN ANALYSIS OF A PREPACKAGED NUCLEAR POWER PLANT (1000 eKW). VOLUME I. PRIMARY AND SECONDARY SYSTEM DESIGN
Technical Report
·
Sat Jan 31 23:00:00 EST 1959
·
OSTI ID:4177874
Retrofit utility power plant to combined cycle operation
Conference
·
Thu Dec 31 23:00:00 EST 1987
· Proceedings of the American Power Conference; (USA)
·
OSTI ID:7229209