PATHFINDER ATOMIC POWER PLANT FINAL REPORT MOISTURE DE-ENTRAINMENT TESTS IN TWO- AND FOUR-INCH DIAMETER TEST SECTIONS
Tests are described to determine the amount of entrained moisture occurring in the steam of the Pathfinder Power Plant as design parameters were varied. It was found that the height of the moisture separator and the velocity of the steam should be adjusted so that the permissible steam velocity for the particular height is not exceeded. If this is done, the amount of moisture entering the separator should be less than 1%, an amount of moisture that should not be difficult to remove with moisture separators. (J.R.D.)
- Research Organization:
- Allis-Chalmers Mfg. Co. Atomic Energy Div., Milwaukee
- NSA Number:
- NSA-14-004115
- OSTI ID:
- 4208114
- Report Number(s):
- ACNP-5921
- Country of Publication:
- United States
- Language:
- English
Similar Records
REMOVAL OF ENTRAINED MOISTURE FROM STEAM USING NATURAL SEPARATION AND MECHANICAL DRYERS. Pathfinder Atomic Power Plant, Final Summary Report
PATHFINDER ATOMIC POWER PLANT STEAM SEPARATOR DEVELOPMENT
The Moisture Separation in BWR
Technical Report
·
Fri Apr 14 23:00:00 EST 1961
·
OSTI ID:4046544
PATHFINDER ATOMIC POWER PLANT STEAM SEPARATOR DEVELOPMENT
Technical Report
·
Fri Jun 15 00:00:00 EDT 1962
·
OSTI ID:4785350
The Moisture Separation in BWR
Journal Article
·
Sat Dec 31 23:00:00 EST 1960
· Nippon Genshiryoku Gakkai-Shi
·
OSTI ID:4819043