SM-2 6000 & 12000 eKW NUCLEAR POWER PLANT PRIMARY SYSTEM DESIGN
The development studies for an SM-2 Nuclear Power Plant primary system are summarized. The studies include the following: horizortal steam generator, safety and alarm system, decontamination methods, waste disposal, preassembly and packaging, vapor container, vertical steam generator and feedwater control system, pressurizer development and design studies, fuel handling, superheater, and instrumertation. The design analysis for the main primary system and the primary auxiliary sysdescriptions. The results obtained from the development studies and design analysis are included for a 6000 kw(e) plant design which utilizes a single 28 Mw(t) reactor system, and for the preliminary design of a 12,000 kw(e) plant design which utilizes two identical 28 Mw(t) reactor systems. (auth)
- Research Organization:
- Alco Products, Inc., Schenectady, N.Y.
- DOE Contract Number:
- DA-44-192-ENG-7
- NSA Number:
- NSA-15-024579
- OSTI ID:
- 4026310
- Report Number(s):
- APAE-74(Vol.I)
- Resource Relation:
- Other Information: Orig. Receipt Date: 31-DEC-61
- Country of Publication:
- United States
- Language:
- English
Similar Records
SM-2 6000 eKW (NET) NUCLEAR POWER PLANT FINAL DESIGN SECONDARY SYSTEM
SM-2 6000 & 12000 eKW NUCLEAR POWER PLANT PRIMARY SYSTEM DESIGN ANALYSIS CALCULATIONS