Florida Power Corporation recently completed a Fossil Plant Maintenance Optimization project at it`s Crystal River Units 4 and 5 coal fired power plant. The project combined Streamlined Reliability Centered Maintenance (SRCM) techniques with a Predictive Maintenance (PDM) Assessment to analyze eleven of the plants systems that represent the principal contributors to maintenance costs. The plant had an extensive existing maintenance program that included several types of condition monitoring. The Benefit-to-Cost analysis indicates that the annual savings associated with the project recommendations result in a payback period of less than one year. This paper summarizes the types of recommendations that were made and describes the processes used for both the SRCM analysis and the PDM Assessment. The SRCM analysis used proven techniques and software that have been used on other projects, including some sponsored by EPRI. The PDM Assessment process was similar to processes used previously for EPRI and non- EPRI utilities; however, this was the first project where the two processes were modified to take advantage of work performed using the other. All of the recommendations developed by the SRCM analysts were reviewed by the PDM analysts before they were finalized. The structure and flow of the project is also described including how the SRCM and PDM analysts interfaced with the plant staff and how implementation was facilitated. The analysis relied on plant experience related to the operation and maintenance history of the equipment. The recommendations for each system were reviewed by a team consisting of the first-line maintenance supervisors, the maintenance planners, and the plant technical services group. The project recommendations are essentially two-thirds implemented, with many of them implemented before the analysis was completed.

Research Organization:
Electric Power Research Inst., Palo Alto, CA (United States); Baltimore Gas and Electric Co., MD (United States)
OSTI ID:
401920
Report Number(s):
EPRI-TR--106753; CONF-960719--
Country of Publication:
United States
Language:
English

Similar Records

Streamlined RCM at TU electric
Technical Report · Mon Jul 01 00:00:00 EDT 1996 · OSTI ID:401945

Streamlined reliability-centered maintenance (SRCM) program for hydroelectric power plants. Final report
Technical Report · Sat Oct 31 23:00:00 EST 1998 · OSTI ID:10140142

Substations reliability-centered maintenance and predictive maintenance - a strategic partnership
Technical Report · Thu Aug 01 00:00:00 EDT 1996 · OSTI ID:430406