Tillery Dam is located approximately 50 miles east of Charlotte, North Carolina, on the Pee Dee River. Construction of the project was completed in 1928 and, beginning from the east side of the project, it consists of a powerhouse and intake section and east nonoverflow section totaling 618 feet long with a maximum height of 98.5 feet above the rock foundation. The concrete spillway is 758 feet long with 18 34-foot-wide by 24-foot-high tainter gates mounted on a 62-foot-high ogee section with a concrete stilling basin. The west nonoverflow section is 176 feet long. The west end of the project consists of a 1,200-foot-long earth embankment with a maximum height of 77 feet above the cut-off trench that extends to rock. Carolina Power & Light (CP&L) owns the project and operates the facility in accordance with its license issued by the Federal Energy Regulatory Commission (FERC). In 1990, during the review of a safety inspection report submitted by CP&L and its consultant, FERC made several comments concerning the concrete gravity and embankment structures.
OSTI ID:
220011
Report Number(s):
CONF-9507190--
Country of Publication:
United States
Language:
English

Similar Records

Amistad power plant. Final foundation report
Technical Report · Sat Oct 01 00:00:00 EDT 1983 · OSTI ID:5260813

Saxon Falls Dam rehabilitation
Conference · Sat Dec 30 23:00:00 EST 1995 · OSTI ID:220024

Foote Hydroelectric Plant spillway rehabilitation
Conference · Tue Oct 01 00:00:00 EDT 1996 · OSTI ID:376182