Transition projects, Fiscal Year 1996: Multi-Year Program Plan (MYPP) for WBS 1.31, 7.1, and 6.13. Revision 1, Volume 1
Based on US Department of Energy (DOE), Richland Operations Office (RL) review, specific areas of Westinghouse Hanford Company (WHC), Transition Projects ``Draft`` Multi-Year Program Plan (MYPP) were revised in preparation for the RL approval ceremony on September 26, 1995. These changes were reviewed with the appropriate RL Project Manager. The changes have been incorporated to the MYPP electronic file, and hard copies replacing the ``Draft`` MYPP will be distributed after the formal signing. In addition to the comments received, a summary level schedule and outyear estimates for the K Basin deactivation beginning in FY 2001 have been included. The K Basin outyear waste data is nearing completion this week and will be incorporated. This exclusion was discussed with Mr. N.D. Moorer, RL, Facility Transition Program Support/Integration. The attached MYPP scope/schedule reflects the Integrated Target Case submitted in the April 1995 Activity Data Sheets (ADS) with the exception of B Plant and the Plutonium Finishing Plant (PFP). The 8 Plant assumption in FY 1997 reflects the planning case in the FY 1997 ADS with a shortfall of $5 million. PFP assumptions have been revised from the FY 1997 ADS based on the direction provided this past summer by DOE-Headquarters. This includes the acceleration of the polycube stabilization back to its originally planned completion date. Although the overall program repricing in FY 1996 allowed the scheduled acceleration to fall with the funding allocation, the FY 1997 total reflects a shortfall of $6 million.
- Research Organization:
- Westinghouse Hanford Co., Richland, WA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-87RL10930
- OSTI ID:
- 123597
- Report Number(s):
- WHC-SP--1126-Rev.1-Vol.1; ON: DE96001581
- Country of Publication:
- United States
- Language:
- English
Similar Records
Planning integration FY 1995 Multi-Year Program Plan (MYPP)/Fiscal Year Work Plan (FYWP)
Fiscal year (FY) 1989 defense waste management and environmental program plan; Revision 2
Environmental support FY 1995 multi-year program plan/fiscal year work plan WBS 1.5.2/7.4.11
Technical Report
·
Thu Sep 01 00:00:00 EDT 1994
·
OSTI ID:10188613
Fiscal year (FY) 1989 defense waste management and environmental program plan; Revision 2
Technical Report
·
Fri Jun 30 00:00:00 EDT 1989
·
OSTI ID:719906
Environmental support FY 1995 multi-year program plan/fiscal year work plan WBS 1.5.2/7.4.11
Technical Report
·
Thu Sep 01 00:00:00 EDT 1994
·
OSTI ID:10118937