Decontamination and dismantlement of the building 200/205 pneumatic transfer tube at Argonne National Laboratory-East project final report.
The Building 200/205 Pneumatic Transfer Tube D&D Project was directed toward the following goals: Remove any radioactive and hazardous materials associated with the transfer tube; Survey the transfer tube to identify any external contamination; Remove the transfer tube and package for disposal; Survey the soil and sand surrounding the transfer tube for any contamination; and Backfill the trench in which the tube sat and restore the area to its original condition. These goals had been set in order to eliminate the radiological and hazardous safety concerns inherent in the buried transfer tube and to allow, upon completion of the project, the removal of this project from the ANL-E action item list. The physical condition of the transfer tube and possible nuclear fuel samples lost in the tube were the primary areas of concern, while the exact location of the transfer tube was of secondary concern. ANL-E health physics technicians collected characterization data from the ends of the Building 200/205 pneumatic transfer tube in January 1998. The characterization surveys identified contamination to a level of 67,000 dpm (1,117 Bq) ({beta}/{gamma}) and 20,000 dpm (333 Bq) {alpha} smearable at the opening.
- Research Organization:
- Argonne National Lab., IL (US)
- Sponsoring Organization:
- US Department of Energy (US)
- DOE Contract Number:
- W-31109-ENG-38
- OSTI ID:
- 12331
- Report Number(s):
- ANL/D& D/98-5
- Country of Publication:
- United States
- Language:
- English
Similar Records
Decontamination and dismantlement of the building 594 waste ion exchange facility at Argonne National Laboratory-East project final report.
Radiological survey techniques for decontamination and dismantlement applications