NSLS-II injector commissioning and initial operation

Conference ·
OSTI ID:1193208

The injector for the National Synchrotron Light Source II (NSLS-II) storage ring consists of a 3 GeV booster synchrotron and a 200 MeV S-band linac. The linac was designed to produce either a single bunch with a charge of 0.5 nC of electrons or a train of bunches up to 300 ns long containing a total charge of 15 nC. The booster was designed to accelerate up to 15 nC each cycle in a train of bunches up to 300 ns long. Linac commissioning was completed in April 2012. Booster commissioning was started in November 2013 and completed in March 2014. All of the significant design goals were satisfied including beam emittance, energy spread, and transport efficiency. While the maximum booster charge accelerated was only 10 nC, this has proven to be more than sufficient for storage ring commissioning and operation. The injector has operated reliably during storage ring operation since then. Results will be presented showing measurements of linac and booster operating parameters achieved during commissioning and initial operation. Operating experience and reliability during the first year of NSLS-II operation will be discussed.

Research Organization:
Brookhaven National Laboratory (BNL)
Sponsoring Organization:
USDOE Office of Science (SC)
OSTI ID:
1193208
Report Number(s):
BNL--107993-2015-CP
Country of Publication:
United States
Language:
English

Similar Records

SIMULATIONS OF TRANSVERSE STACKING IN THE NSLS-II BOOSTER
Conference · Mon Mar 28 00:00:00 EDT 2011 · OSTI ID:1013533

NSLS-II Booster Design
Technical Report · Sun Nov 15 23:00:00 EST 2009 · OSTI ID:1480933

Validation of Analytical Calculations for the NSLS-II Injection Shutters with FLUKA Monte-Carlo Program
Technical Report · Thu Jul 17 00:00:00 EDT 2014 · OSTI ID:1493211

Related Subjects