TIDD PFBC demonstration project. Quarterly report, January--March 1995
This is the thirty-second Technical Progress Report submitted to the Department of Energy in connection with the Cooperative Agreement between the DOE and the Ohio Power Company for the Tidd PFBC Demonstration Plant. This report covers the period from January 1, 1995 to March 31, 1995. Major Activities during this period include: The unit operated for 718 hours on coal, bringing the grand total for coal fire through the end of the quarter to 11,442 hours. There were seven gas turbine starts, nine bed preheater starts, and nine operating periods on coal. During this quarter, total gross generation was 57,693 MWH, the peak unit output for one hour was 74 MWH, and the coal consumption was 27,866 tons. Twelve performance tests were conducted during this quarter, bringing the total number of tests for the plant to 95. On March 30,1995, at 8:27 am, the Tidd PFBC Demonstration Plant was manually tripped for the last time.
- Research Organization:
- American Electric Power Service Corp., Columbus, OH (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- FC21-87MC24132
- OSTI ID:
- 110789
- Report Number(s):
- DOE/MC/24132--5002; ON: DE95009738
- Country of Publication:
- United States
- Language:
- English
Similar Records
Tidd PFBC Demonstration Project. Quarterly report, January--March 1994
TIDD PFBC Demonstration Project. Quarterly report, July--September 1994
Tidd PFBC demonstration project: Technical progress report, third quarter 1994
Technical Report
·
Thu Mar 31 23:00:00 EST 1994
·
OSTI ID:10157759
TIDD PFBC Demonstration Project. Quarterly report, July--September 1994
Technical Report
·
Sat Dec 31 23:00:00 EST 1994
·
OSTI ID:101178
Tidd PFBC demonstration project: Technical progress report, third quarter 1994
Technical Report
·
Sat Oct 01 00:00:00 EDT 1994
·
OSTI ID:46623