Summary report for the tank tightness testing of underground storage tanks, Idaho National Engineering Laboratory
Between August 14, 1989, and August 26, 1989, 16 underground storage tanks were tank tightness tested for leaks as part of the Idaho National Engineering Laboratory tank management program. This report summarizes the results of these tank tightness tests, the modifications and repairs made to the tank systems, fuel transfer records, and any problems that affected the tank testing schedule. Of the 16 underground storage tanks tested, five failed the tank tightness test. Attempts were made to repair the tanks that failed the tank tightness test. Of those tanks, two were tested three times (one passed and one failed), and three were tested twice (two passed and one failed). The five failed tanks were removed and will be replaced with tanks that meet the Environmental Protection Agency regulations of underground storage tanks. 3 refs., 1 fig., 3 tabs.
- Research Organization:
- EG and G Idaho, Inc., Idaho Falls, ID (USA)
- Sponsoring Organization:
- DOE/NE
- DOE Contract Number:
- AC07-76ID01570
- OSTI ID:
- 6710683
- Report Number(s):
- EGG-ESQ-8888; ON: DE90015820
- Country of Publication:
- United States
- Language:
- English
Similar Records
Closure report for underground storage tank 161-R1U1 and its associated underground piping
Leak tightness testing of underground tank systems
Related Subjects
DIESEL FUELS
UNDERGROUND STORAGE
GASOLINE
KEROSENE
LIQUIDS
TANKS
LEAK TESTING
EXPERIMENTAL DATA
IDAHO NATIONAL ENGINEERING LABORATORY
LEAKS
MODIFICATIONS
REPAIR
CONTAINERS
DATA
FLUIDS
FUELS
INFORMATION
LIQUID FUELS
NATIONAL ORGANIZATIONS
NUMERICAL DATA
PETROLEUM PRODUCTS
STORAGE
TESTING
US DOE
US ERDA
US ORGANIZATIONS
420205* - Engineering- Transport & Storage Facilities- (1980-)