Title: Long term pre-qualification testing program on a 230kV XLPE cable system

Journal Article · · IEEE Transactions on Power Delivery
DOI:https://doi.org/10.1109/61.368421· OSTI ID:39964
 [1];  [2];  [3]
  1. Georgia Power Research Center, Forest Park, GA (United States)
  2. Pirelli Cable Corp., Greenwood, SC (United States)
  3. Pirelli Cables Ltd., Hampshire (United Kingdom)

This paper describes the installation, testing, and results of a long term, full scale laboratory evaluation of a 230kV XLPE insulated cable system. System components included two innovative, pre-molded splices, a 128 meter (420 foot) cable run, and two silicone oil filled, porcelain cable terminations. Load cycle aging was performed on the cable system over a four year period. After successfully completing the outdoor aging program, the system was exposed to a final impulse breakdown test. Results demonstrated the importance or considering thermomechanical bending in aluminum conductor, XLPE insulated designs. The influence on cable ampacity of solar beating at riser transitions was also demonstrated.

OSTI ID:
39964
Report Number(s):
CONF-9404175-; ISSN 0885-8977; TRN: IM9520%%158
Journal Information:
IEEE Transactions on Power Delivery, Vol. 10, Issue 1; Conference: Institute of Electrical and Electronics Engineers/Power Engineering Society (IEEE/PES) transmission and distribution conference, Chicago, IL (United States), 10-15 Apr 1994; Other Information: PBD: Jan 1995