Title: Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103

Abstract

This letter serves as the post-closure monitoring letter report for the above Corrective Action Unit (CAU) for the period October 2006-September 2007. Quarterly inspections were conducted on December 20,2006; March 29,2007; June 13,2007; and September 27, 2007, to observe the condition of the gate, use restriction warning signs, monuments, fencing, trenches, soil covers, and monitoring well covers. The first inspection was conducted on December 20,2006. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The second inspection was conducted on March 29,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. Vegetation that was observed to be growing in several locations on the cover was the only identified concern, for which removal was recommended. Vegetation was removed on May 24,2007. The third inspection was conducted on June 13,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended.more » The fourth inspection was conducted on September 27,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The post-closure inspection checklists for CAU 112 are attached. Photographs and field notes taken during site inspections are maintained in the project files.« less

Authors:
Publication Date:
Research Org.:
National Security Technologies, LLC
Sponsoring Org.:
USDOE - National Nuclear Security Administration (NNSA)
OSTI Identifier:
926205
Report Number(s):
DOE/NV-1103-LR; DOE/NV/25946-367
TRN: US0803436
DOE Contract Number:  
DE-AC52-06NA25946
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
54 ENVIRONMENTAL SCIENCES; 12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; IMAGES; MONITORING; NEVADA TEST SITE; PLANTS; REMOVAL; SOILS; WASTES; Post-Closure Letter Report CAU 112

Citation Formats

NSTec Environmental Restoration. Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103. United States: N. p., 2008. Web. doi:10.2172/926205.
NSTec Environmental Restoration. Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103. United States. doi:10.2172/926205.
NSTec Environmental Restoration. Wed . "Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103". United States. doi:10.2172/926205. https://www.osti.gov/servlets/purl/926205.
@article{osti_926205,
title = {Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103},
author = {NSTec Environmental Restoration},
abstractNote = {This letter serves as the post-closure monitoring letter report for the above Corrective Action Unit (CAU) for the period October 2006-September 2007. Quarterly inspections were conducted on December 20,2006; March 29,2007; June 13,2007; and September 27, 2007, to observe the condition of the gate, use restriction warning signs, monuments, fencing, trenches, soil covers, and monitoring well covers. The first inspection was conducted on December 20,2006. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The second inspection was conducted on March 29,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. Vegetation that was observed to be growing in several locations on the cover was the only identified concern, for which removal was recommended. Vegetation was removed on May 24,2007. The third inspection was conducted on June 13,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The fourth inspection was conducted on September 27,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The post-closure inspection checklists for CAU 112 are attached. Photographs and field notes taken during site inspections are maintained in the project files.},
doi = {10.2172/926205},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2008},
month = {1}
}