Heber geothermal binary demonstration project quarterly technical progress report, October 1, 1981--December 31, 1981
The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of October 1, 1981, through December 31, 1981. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.
- Research Organization:
- San Diego Gas & Electric, San Diego, CA
- Sponsoring Organization:
- USDOE
- DOE Contract Number:
- FC03-80RA50239
- OSTI ID:
- 895642
- Report Number(s):
- SAN/RA50239-SDGE-0009
- Country of Publication:
- United States
- Language:
- English
Similar Records
Heber geothermal binary demonstration project quarterly technical progress report, July 1, 1981--September 30, 1981
Heber geothermal binary demonstration project quarterly technical progress report, January 1, 1982--March 31, 1982
Heber geothermal binary demonstration project quarterly technical progress report, April 1, 1982--June 30, 1982
Technical Report
·
Mon Aug 01 00:00:00 EDT 1983
·
OSTI ID:895640
Heber geothermal binary demonstration project quarterly technical progress report, January 1, 1982--March 31, 1982
Technical Report
·
Mon Aug 01 00:00:00 EDT 1983
·
OSTI ID:895645
Heber geothermal binary demonstration project quarterly technical progress report, April 1, 1982--June 30, 1982
Technical Report
·
Mon Aug 01 00:00:00 EDT 1983
·
OSTI ID:895658