HANFORD PLUTONIUM FINISHG PLAN (PFP) COMPLETES PLUTONIUM STABILIZATION KEY SAFETY ISSUES CLOSED
Journal Article
·
· Radwaste Solutions
OSTI ID:821830
- FH
A long and intense effort to stabilize and repackage nearly 18 metric tons (MT) of plutonium-bearing leftovers from defense production and nuclear experiments concluded successfully in February, bringing universal congratulations to the Department of Energy's Hanford Site in southeast Washington State. The victorious stabilization and packaging endeavor at the Plutonium Finishing Plant (PFP), managed and operated by prime contractor Fluor Hanford, Inc., finished ahead of all milestones in Hanford's cleanup agreement with regulators, and before deadlines set by the Defense Nuclear Facilities Safety Board (DNFSB), a part of the federal Executive Branch that oversees special nuclear materials. The PFP stabilization and packaging project also completed under budget for its four-year tenure, and has been nominated for a DOE Secretarial Award. It won the Project of the Year Award in the local chapter competition of the Project Management Institute, and is being considered for awards at the regional and national level.
- Research Organization:
- FH (US)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM) (US)
- DOE Contract Number:
- AC06-96RL13200
- OSTI ID:
- 821830
- Report Number(s):
- HNF-20159-FP, Rev.0
- Journal Information:
- Radwaste Solutions, Journal Name: Radwaste Solutions
- Country of Publication:
- United States
- Language:
- English
Similar Records
PLUTONIUM FINISHING PLANT (PFP) STABILIZATION & PACKAGING PROJECT
THE DEACTIVATION DECONTAMINATION & DECOMMISSIONING OF THE PLUTONIUM FINISHING PLANT (PFP) A FORMER PLUTONIUM PROCESSING FACILITY AT DOE HANFORD SITE
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT (PFP)
Conference
·
Tue Jan 13 23:00:00 EST 2004
·
OSTI ID:821208
THE DEACTIVATION DECONTAMINATION & DECOMMISSIONING OF THE PLUTONIUM FINISHING PLANT (PFP) A FORMER PLUTONIUM PROCESSING FACILITY AT DOE HANFORD SITE
Conference
·
Tue Jan 31 23:00:00 EST 2006
·
OSTI ID:875914
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT (PFP)
Technical Report
·
Sun Jan 21 23:00:00 EST 2001
·
OSTI ID:820845