Title: Accelerated Closure of the Spent Nuclear Fuel (SNF) project

Abstract

The K East and K West Basins, built in the early 1950s, have been used to store irradiated nuclear fuel from the Hanford N Reactor. This fuel, which is referred to as spent nuclear fuel (SNF), has been stored underwater since 1975 in KE Basin and since 1981 in KW Basin. There are 54,000 N Reactor fuel assemblies in 3,800 canisters in the K West Basin, and 51,000 fuel assemblies in 3,700 canisters in the K East Basin that total 2,100 metric tons of SNF.

Authors:
Publication Date:
Research Org.:
FH (US)
Sponsoring Org.:
USDOE Office of Environmental Management (EM) (US)
OSTI Identifier:
806003
Report Number(s):
HNF-7709-FP, Rev.0
TRN: US0301078
DOE Contract Number:
AC06-96RL13200
Resource Type:
Conference
Resource Relation:
Conference: Conference title not supplied, Conference location not supplied, Conference dates not supplied; Other Information: PBD: 1 Feb 2001
Country of Publication:
United States
Language:
English
Subject:
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; CLOSURES; CONTAINERS; FUEL ASSEMBLIES; METRICS; N-REACTOR; NUCLEAR FUELS

Citation Formats

RUTHERFORD, W.W. Accelerated Closure of the Spent Nuclear Fuel (SNF) project. United States: N. p., 2001. Web.
RUTHERFORD, W.W. Accelerated Closure of the Spent Nuclear Fuel (SNF) project. United States.
RUTHERFORD, W.W. 2001. "Accelerated Closure of the Spent Nuclear Fuel (SNF) project". United States. doi:. https://www.osti.gov/servlets/purl/806003.
@article{osti_806003,
title = {Accelerated Closure of the Spent Nuclear Fuel (SNF) project},
author = {RUTHERFORD, W.W.},
abstractNote = {The K East and K West Basins, built in the early 1950s, have been used to store irradiated nuclear fuel from the Hanford N Reactor. This fuel, which is referred to as spent nuclear fuel (SNF), has been stored underwater since 1975 in KE Basin and since 1981 in KW Basin. There are 54,000 N Reactor fuel assemblies in 3,800 canisters in the K West Basin, and 51,000 fuel assemblies in 3,700 canisters in the K East Basin that total 2,100 metric tons of SNF.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = 2001,
month = 2
}

Conference:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that hold this conference proceeding.

Save / Share:
  • A carbon steel storage canister has been designed for the dry encapsulation of spent nuclear fuel assemblies or of logs of vitrified high level radioactive waste. The canister design is in conformance with the requirements of the ASME Code, Section III, Division 1 for a Class 3 vessel. The canisters will be loaded and sealed as part of a completely remote process sequence to be performed in the hot bay of an experimental encapsulation facility at the Nevada Test Site. The final closure to be made is a full penetration butt weld between the canister body, a 12.75-in O.D. xmore » 0.25-in wall pipe, and a mating semiellipsoidal closure lid. Due to a combination of design, application and facility constraints, the closure weld must be made in the 2G position (canister vertical). The plasma arc welding system is described, and the final welding procedure is described and discussed in detail. Several aspects and results of the procedure development activity, which are of both specific and general interest, are highlighted; these include: The critical welding torch features which must be exactly controlled to permit reproducible energy input to, and gas stream interaction with, the weld puddle. A comparison of results using automatic arc voltage control with those obtained using a mechanically fixed initial arc gap. The optimization of a keyhole initiation procedure. A comparison of results using an autogenous keyhole closure procedure with those obtained using a filler metal addition. The sensitivity of the welding process and procedure to variations in joint configuration and dimensions and to variations in base metal chemistry. Finally, the advantages and disadvantages of the plasma arc process for this application are summarized from the current viewpoint, and the applicability of this process to other similar applications is briefly indicated.« less
  • The National Spent Nuclear Fuel Program (NSNFP) has developed standardized DOE SNF canisters for handling and interim storage of SNF at various DOE sites as well as SNF transport to and SNF handling and disposal at the repository. The final closure weld of the canister will be produced remotely in a hot cell after loading and must meet American Society of Mechanical Engineers (ASME) Section III, Division 3 code requirements thereby requiring volumetric and surface nondestructive evaluation to verify integrity. This paper discusses the use of eddy current testing (ET) to perform surface examination of the completed welds and repairmore » cavities. Descriptions of integrated remote welding/inspection system and how the equipment is intended function will also be discussed.« less
  • Fluor engineers developed a Gas Tungsten Arc Welding (GTAW) technique and parameters, demonstrated requisite weld quality, and successfully closure-welded packaged spent nuclear fuel (SNF) overpacks at the Hanford Site. This paper reviews weld development and qualification activities associated with the overpack closure-welding and provides a summary of the production campaign. The primary requirement of the closure weld is to provide leak-tight confinement of the packaged material against release to the environment during interim storage (40-year design term). Required weld quality, in this case, was established through up-front development and qualification, and then verification of parameter compliance during production welding. Thismore » approach was implemented to allow for a simpler overpack design and more efficient production operations than possible with approaches using routine post-weld testing and nondestructive examination (NDE). A series of welding trials were conducted to establish the desired welding technique and parameters. Qualification of the process included statistical evaluation and American Society of Mechanical Engineers (ASME) Section IX testing. In addition, pull testing with a weighted mockup, and thermal calculation/physical testing to identify the maximum temperature the packaged contents would be subject to during welding, was performed. Thirteen overpacks were successfully packaged and placed into interim storage. The closure-welding development activities (including pull testing and thermal analysis) provided the needed confidence that the packaged SNF overpacks could be safely handled and placed into interim storage, and remain leak-tight for the duration of the storage term. (author)« less
  • Fluor engineers developed a Gas Tungsten Arc Welding (GTAW) technique and parameters, demonstrated requisite weld quality and successfully closure-welded packaged spent nuclear fuel (SNF) overpacks at the Hanford Site. This paper reviews weld development and qualification activities associated with the overpack closure-welding and provides a summary of the production campaign. The primary requirement of the closure weld is to provide leaktight confinement of the packaged material against release to the environment during interim storage (40-year design term). Required weld quality, in this case, was established through up-front development and qualification, and then verification of parameter compliance during production welding. Thismore » approach was implemented to allow for a simpler overpack design and more efficient production operations than possible with approaches using routine post-weld testing and nondestructive examination (NDE). . A series of welding trials were conducted to establish the desired welding technique and parameters. Qualification of the process included statistical evaluation and American Society of Mechanical Engineers (ASME) Section IX testing. In addition, pull testing with a weighted mockup, and thermal calculation/physical testing to identify the maximum temperature the packaged contents would be subject to during welding, was performed. Thirteen overpacks were successfully packaged and placed into interim storage. The closure-welding development activities (including pull testing and thermal analysis) provided the needed confidence that the packaged SNF overpacks could be safely handled and placed into interim storage, and remain leaktight for the duration of the storage term.« less
  • This paper highlights progress made during the last year toward removing the Department of Energy`s (DOE) approximately, 2,100 metric tons of metallic spent nuclear fuel from the two outdated K Basins at the Hanford Site and placing it in safe, economical interim dry storage. In the past year, the Spent Nuclear Fuel (SNF) Project has engaged in an evolutionary process involving the customer, regulatory bodies, and the public that has resulted in a quicker, cheaper, and safer strategy for accomplishing that goal. Development and implementation of the Integrated Process Strategy for K Basins Fuel is as much a case studymore » of modern project and business management within the regulatory system as it is a technical achievement. A year ago, the SNF Project developed the K Basins Path Forward that, beginning in December 1998, would move the spent nuclear fuel currently stored in the K Basins to a new Staging and Storage Facility by December 2000. The second stage of this $960 million two-stage plan would complete the project by conditioning the metallic fuel and placing it in interim dry storage by 2006. In accepting this plan, the DOE established goals that the fuel removal schedule be accelerated by a year, that fuel conditioning be closely coupled with fuel removal, and that the cost be reduced by at least $300 million. The SNF Project conducted coordinated engineering and technology studies over a three-month period that established the technical framework needed to design and construct facilities, and implement processes compatible with these goals. The result was the Integrated Process Strategy for K Basins Fuel. This strategy accomplishes the goals set forth by the DOE by beginning fuel removal a year earlier in December 1997, completing it by December 1999, beginning conditioning within six months of starting fuel removal, and accomplishes it for $340 million less than the previous Path Forward plan.« less