Title: Activity Based Startup Plan for Prototype Vertical Denitration Calciner

Abstract

Testing activities on the Prototype Vertical Denitration Calciner at PFP were suspended in January 1997 due to the hold on fissile material handling in the facility. The restart of testing activities will require a review through an activity based startup process based upon Integrated Safety Management (ISM) principles to verify readiness. The Activity Based Startup Plan has been developed for this process.

Authors:
Publication Date:
Research Org.:
BWHC (US)
Sponsoring Org.:
ENVIRONMENTAL MANAGEMENT (US)
OSTI Identifier:
797707
Report Number(s):
HNF-4522, Rev.1
TRN: US0204981
DOE Contract Number:
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 31 Aug 1999
Country of Publication:
United States
Language:
English
Subject:
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; DENITRATION; FISSILE MATERIALS; MANAGEMENT; SAFETY; TESTING

Citation Formats

SUTTER, C.S. Activity Based Startup Plan for Prototype Vertical Denitration Calciner. United States: N. p., 1999. Web. doi:10.2172/797707.
SUTTER, C.S. Activity Based Startup Plan for Prototype Vertical Denitration Calciner. United States. doi:10.2172/797707.
SUTTER, C.S. 1999. "Activity Based Startup Plan for Prototype Vertical Denitration Calciner". United States. doi:10.2172/797707. https://www.osti.gov/servlets/purl/797707.
@article{osti_797707,
title = {Activity Based Startup Plan for Prototype Vertical Denitration Calciner},
author = {SUTTER, C.S.},
abstractNote = {Testing activities on the Prototype Vertical Denitration Calciner at PFP were suspended in January 1997 due to the hold on fissile material handling in the facility. The restart of testing activities will require a review through an activity based startup process based upon Integrated Safety Management (ISM) principles to verify readiness. The Activity Based Startup Plan has been developed for this process.},
doi = {10.2172/797707},
journal = {},
number = ,
volume = ,
place = {United States},
year = 1999,
month = 8
}

Technical Report:

Save / Share:
  • Testing activities on the Prototype Vertical Denitration Calciner at Plutonium Finish Plant (PFP) were suspended in January 1997 due to the hold on fissile material handling in the facility. The restart of testing activities will require a review through an activity based startup process based upon Integrated Safety Management (ISM) principles to verify readiness. The Activity Based Startup Plan for the Prototype vertical Denitration Calciner has been developed for this process.
  • Testing activities on the Prototype Vertical Denitration Calciner at PFP were suspended in January 1997 due to the hold on fissile material handling in the facility. The Restart Plan will govern the transition of the test program from the completion of the activity based startup review; through equipment checkout and surrogate material runs; to resumption of the testing program and transition to unrestricted testing.
  • Testing activities on the Prototype Vertical Denitration Calciner at the Plutonium Finishing Plant (PFP) were suspended in January 1997 due to the hold on fissile material handling in the facility. The Restart Plan will govern the transition of the test program from the completion of the activity based startup review; through equipment checkout and surrogate material runs; to resumption of the testing program and transition to unrestricted testing.
  • Testing activities on the Prototype Vertical Denitration Calciner at the Plutonium Finishing Plant (PFP) were suspended in January 1997 due to the hold on fissile material handling in the facility. The Restart Plan will govern the transition of the test program from the completion of the activity based startup review; through equipment checkout and surrogate material runs; to resumption of the testing program and transition to unrestricted testing.
  • Testing activities on the Prototype Vertical Denitration Calciner at PFP were suspended in January 1997 due to the hold on fissile material handling in the facility. The Restart Plan will govern the transition of the test program from the completion of the activity based startup review; through equipment checkout and surrogate material runs; to resumption of the testing program and transition to unrestricted testing.