Fast flux test facility performance monitoring management information, May 1988
The plant operated at full power until May 6 when it was shut down for a planned outage for refueling and maintenance. The success of outage activity placed it slightly ahead of the 37-day outage schedule at month`s end. Operational efficiency in May was again 100%. The plant has operated over 110 effective full power days this year through Cycle 10A. As a result, the plant remains on target for meeting the 96% Operational Efficiency Factor and 70% Capacity Factor goals for 1988. Focus on outage activity resulted in little progress on further reduction of maintenance backlogs. An unfavorable trend was experienced in spare parts availability and a slight increase in overdue commitments. Otherwise, there were no significant trends apparent in May.
- Research Organization:
- Westinghouse Hanford Co., Richland, WA (United States)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM)
- DOE Contract Number:
- AC06-87RL10930
- OSTI ID:
- 719167
- Report Number(s):
- WHC-SP-0081-10; ON: TI88013390
- Country of Publication:
- United States
- Language:
- English
Similar Records
Fast Flux Test Facility performance monitoring management information December 1988
Fast Flux Test Facility Performance Monitoring Management Information March 1988
Fast Flux Test Facility Performance Monitoring Management Information February 1989
Technical Report
·
Sat Dec 31 23:00:00 EST 1988
·
OSTI ID:719567
Fast Flux Test Facility Performance Monitoring Management Information March 1988
Technical Report
·
Thu Mar 31 23:00:00 EST 1988
·
OSTI ID:719115
Fast Flux Test Facility Performance Monitoring Management Information February 1989
Technical Report
·
Tue Feb 28 23:00:00 EST 1989
·
OSTI ID:719651