Final audit report of remedial action construction at the UMTRA Project, Grand Junction, Colorado, processing site
This final audit report (FAR) for remedial action at the Grand Junction, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project processing site consists of a summary of the radiological surveillances/ audits, the quality assurance (QA) in-process surveillances, and the QA final close-out inspection performed by the US Department of Energy (DOE) and Technical Assistance Contractor (TAC). The FAR also summarizes other surveillances performed by the US Nuclear Regulatory Commission (NRC). To summarize, a total of one finding and 127 observations were noted during DOE/TAC audit and surveillance activities. The NRC noted general site-related observations during the OSCRs. Follow-up to responses required from MK-Ferguson for the DOE/TAC finding and observations indicated that all issues related to the Grand Junction processing site were resolved and closed out to the DOE`s satisfaction. The NRC OSCRs resulted in no issues related to the Grand Junction processing site requiring a response from MK-Ferguson.
- Research Organization:
- Jacobs Engineering Group, Inc., Albuquerque, NM (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC04-91AL62350
- OSTI ID:
- 71315
- Report Number(s):
- DOE/AL/62350--183; ON: DE95011231
- Country of Publication:
- United States
- Language:
- English
Similar Records
Final audit report of remedial action construction at the UMTRA Project Ambrosia Lake, New Mexico, site
Final audit report of remedial action construction at the UMTRA Project Site, Gunnison, Colorado. Revision 0