Activities remain on schedule to meet the Great Plains Coal Gasification project's full gas production date. Detailed engineering is complete for the gasification plant. The remaining engineering tasks, which include field support activities and special projects, will be performed by the Contractors' Field Engineering Group. A substantial amount of construction progress was achieved during the first quarter. It is currently projected that construction will be complete at the end of September, 1984. Start-Up operations are continuing at a rapid pace. Commissioning activities are proceeding very well. The only remaining plant permit is the Permit to Operate, which will be issued in late 1985. Quality Assurance/Quality Control activities included the development of welding procedures for Operations personnel, safety relief valve testing, and equipment turnover inspections. Mine development activities remain on schedule. Initial coal deliveries to GPGA commenced this quarter.
- Research Organization:
- Great Plains Gasification Associates, Detroit, MI (USA)
- DOE Contract Number:
- FM02-82FE55014
- OSTI ID:
- 6843995
- Report Number(s):
- DOE/FE/55014-T8; ON: DE84010286
- Country of Publication:
- United States
- Language:
- English
Similar Records
Great Plains Gasification Associates. Quarterly technical and environmental report, third quarter, 1983. [Great Plains, Beulah, Mercer County, North Dakota]
Great Plains Coal Gasification Project, Mercer County, North Dakota. Quarterly technical and environmental report, third quarter 1984
Great Plains Coal Gasification Project, Mercer County, North Dakota. Quarterly technical and environmental report, fourth quarter, 1983. [Great Plains, Mercer County, North Dakota]
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:5424089
Great Plains Coal Gasification Project, Mercer County, North Dakota. Quarterly technical and environmental report, third quarter 1984
Technical Report
·
Sat Sep 01 00:00:00 EDT 1984
·
OSTI ID:6087726
Great Plains Coal Gasification Project, Mercer County, North Dakota. Quarterly technical and environmental report, fourth quarter, 1983. [Great Plains, Mercer County, North Dakota]
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:5372091
Related Subjects
01 COAL, LIGNITE, AND PEAT
010404* -- Coal
Lignite
& Peat-- Gasification
012000 -- Coal
Lignite
& Peat-- Mining
ADMINISTRATIVE PROCEDURES
COAL GASIFICATION PLANTS
COAL MINING
CONSTRUCTION
CONTROL
DATA
ENGINEERING
FEDERAL REGION VIII
INDUSTRIAL PLANTS
INFORMATION
MINING
NORTH AMERICA
NORTH DAKOTA
NUMERICAL DATA
PERMIT APPLICATIONS
QUALITY ASSURANCE
QUALITY CONTROL
START-UP
USA
010404* -- Coal
Lignite
& Peat-- Gasification
012000 -- Coal
Lignite
& Peat-- Mining
ADMINISTRATIVE PROCEDURES
COAL GASIFICATION PLANTS
COAL MINING
CONSTRUCTION
CONTROL
DATA
ENGINEERING
FEDERAL REGION VIII
INDUSTRIAL PLANTS
INFORMATION
MINING
NORTH AMERICA
NORTH DAKOTA
NUMERICAL DATA
PERMIT APPLICATIONS
QUALITY ASSURANCE
QUALITY CONTROL
START-UP
USA