MHD ETF conceptual design. Volume I. Summary and recommendations
Three conceptual designs of an MHD Engineering Test Facility (ETF) were defined. The first concept designated, ETF-1 is a complete MHD-steam powerplant with all of the features expected in a large scale commercial unit. The facility was sized compatible with the smallest available modern reheat steam turbine unit. The ETF-2 concept is a facility designed for the purpose of pilot scale demonstration of the major MHD equipment. No steam turbine was included and the size was selected as a minimum felt practical for successful MHD extrapolation to larger commercial sizes. ETF-3 is a facility which initially demonstrates the MHD systems and is later expanded to demonstrate a complete power plant system. It is sized to be compatible in its expanded configuration with the smallest available modern non-reheat steam turbine unit. Performance, costs, schedules and development needs are defined and presented for the three concepts. It is concluded that the ETF-3 concept of an initial MHD oriented facility, to be expanded later into a total power plant, offers the greatest flexibility for cost effective results tailored to technology development.
- Research Organization:
- Westinghouse Electric Corp., Pittsburgh, PA (USA). Advanced Energy Systems Div.
- OSTI ID:
- 6645769
- Report Number(s):
- FE-2363-2(Vol.1)
- Country of Publication:
- United States
- Language:
- English
Similar Records
MHD-ETF design criteria
CDIF combustor design. [For coal-fired MHD generator]
Magnetohydrodynamics (MHD) engineering test facility (ETF) 200 MWe power plant: conceptual design engineering report (CDER). Volume 1. Executive summary
Technical Report
·
Fri Mar 31 23:00:00 EST 1978
·
OSTI ID:6697063
CDIF combustor design. [For coal-fired MHD generator]
Technical Report
·
Tue Jun 01 00:00:00 EDT 1976
·
OSTI ID:7322039
Magnetohydrodynamics (MHD) engineering test facility (ETF) 200 MWe power plant: conceptual design engineering report (CDER). Volume 1. Executive summary
Technical Report
·
Tue Sep 01 00:00:00 EDT 1981
·
OSTI ID:6079258
Related Subjects
30 DIRECT ENERGY CONVERSION
300101* -- MHD Generators-- Design & Development
300102 -- MHD Generators-- Performance & Testing
AUXILIARY SYSTEMS
COAL-FIRED MHD GENERATORS
COMBINED-CYCLE POWER PLANTS
COST
DEMONSTRATION PLANTS
DESIGN
DIRECT ENERGY CONVERTERS
FUNCTIONAL MODELS
MHD GENERATORS
MHD POWER PLANTS
OPEN-CYCLE MHD GENERATORS
PERFORMANCE
PILOT PLANTS
PLANNING
POWER PLANTS
SIZE
STEAM TURBINES
TEST FACILITIES
THERMAL POWER PLANTS
TURBINES
TURBOMACHINERY
300101* -- MHD Generators-- Design & Development
300102 -- MHD Generators-- Performance & Testing
AUXILIARY SYSTEMS
COAL-FIRED MHD GENERATORS
COMBINED-CYCLE POWER PLANTS
COST
DEMONSTRATION PLANTS
DESIGN
DIRECT ENERGY CONVERTERS
FUNCTIONAL MODELS
MHD GENERATORS
MHD POWER PLANTS
OPEN-CYCLE MHD GENERATORS
PERFORMANCE
PILOT PLANTS
PLANNING
POWER PLANTS
SIZE
STEAM TURBINES
TEST FACILITIES
THERMAL POWER PLANTS
TURBINES
TURBOMACHINERY