Heber binary-cycle geothermal power project

Conference ·
OSTI ID:6559586

This paper provides an overview of the 70 MWe Heber Binary Geothermal Demonstration Power Plant. Details of the power conversion cycle, the plant design criteria, mechanical and heat exchange equipment and materials of construction are presented. A review of the construction and start-up milestones and an update of relevant experience gained during the early operation phase of the project is provided. The Heber Binary Project is the first commercial scale binary cycle geothermal power plant commissioned in the United States. San Diego Gas and Electric Company provided overall project management for the project with additional sponsorship support from the Department of Energy, Electric Power Research Institute, four California utilities and two private sector firms.

OSTI ID:
6559586
Report Number(s):
CONF-861005-
Country of Publication:
United States
Language:
English

Similar Records

Heber Binary Project Binary Cycle Geothermal Demonstration Power Plant
Journal Article · Fri Oct 01 00:00:00 EDT 1982 · IEEE Trans. Geosci. Remote Sens.; (United States) · OSTI ID:5318304

Heber binary project
Conference · Wed Aug 01 00:00:00 EDT 1984 · Proc., Intersoc. Energy Convers. Eng. Conf.; (United States) · OSTI ID:5819474

Heber binary-cycle geothermal demonstration power plant: Startup and low-power testing: Special report
Technical Report · Thu Oct 01 00:00:00 EDT 1987 · OSTI ID:5837743