The combined test activities are documented for receiver startup tests for the Barstow Solar Pilot Plant, particularly the receiver cold flow controls preoperational test and the receiver steam generation controls test. Test program and results and supporting data are given for both series of tests. (LEW)
Research Organization:
McDonnell Douglas Astronautics Co., Huntington Beach, CA (USA)
DOE Contract Number:
AC04-76DP00789; AC03-79SF10499
OSTI ID:
6346527
Report Number(s):
MDC-H-0141; ON: DE83009236
Country of Publication:
United States