CO/sub 2/ Acceptor Process Gasification Pilot Plant: commercial plant conceptual design and cost estimate. Final report, Volume 10: Book 3 of 3, Texas lignite gasification, August 1976--December 1977

Technical Report ·
DOI:https://doi.org/10.2172/6318267· OSTI ID:6318267
It is the purpose of this study to estimate the capital, operating cost, and total cost of synthesis gas production using the CO/sub 2/ Acceptor Process. Design of a synthesis gas plant was developed by modifying the design of the North Dakota Lignite Pipeline Gas plant. It is intended that the result of the modifications simulate a CO/sub 2/ Acceptor Plant processing Texas Lignite and producing synthesis gas.
Research Organization:
Conoco Coal Development Co., Library, PA (USA). Research Div.; Stearns-Roger Engineering Co., Denver, CO (USA)
DOE Contract Number:
EX-76-C-01-1734
OSTI ID:
6318267
Report Number(s):
FE-1734-43(Vol.10)(Bk.3)