Decontamination and decommissioning of the SPERT-I seepage pit at the Idaho National Engineering Laboratory. Final report

Technical Report ·
OSTI ID:6158358
This report describes the decontamination and decommissioning of the SPERT-I seepage pit. Prior to its decontamination and decommissioning, the seepage pit was surrounded by an earthen dike varying from 2 to 6 ft above the pit bottom. A 6-in., cast iron, underground waste line originated at the pit tank in the reactor building and ran approximately 68 ft to the seepage pit. The soil in the seepage pit contained low-level radioactive contamination. The soil surface was removed to a depth of 2.5 ft and shipped to the Radioactive Waste Management Complex (RWMC). The waste line that contained fixed contamination was removed and also sent to the RWMC. The pit was backfilled with radiologically clean soil, reducing the surface activity to background. A permanent marker was erected over the backfilled pit to indicate that presence of residual subsurface radioactive contamination. 5 references, 26 figures, 3 tables.
Research Organization:
EG and G Idaho, Inc., Idaho Falls (USA)
DOE Contract Number:
AC07-76ID01570
OSTI ID:
6158358
Report Number(s):
EGG-2291; ON: DE85003273
Country of Publication:
United States
Language:
English