Calculated and measured drift closure during the spent-fuel test in Climax granite

Conference ·
OSTI ID:59245
Horizontal and vertical measurements of drift closures have been made with a manually operated tape extensometer since about 6 weeks after the emplacement of the spent fuel at various locations along the length of the drifts. The averaged closures are less than 0.6 mm from the onset of measurements through about two years after the spent fuel emplacement. These results have been compared with thermo-elastic finite element calculations using measured medium properties. The comparisons show that most of the closure of the drifts occurred between the time the spent fuel was emplaced and the time of first measurement. The comparisons show that the results track each other, in that where closure followed by dilation is measured, the calculations also show this effect. The agreement is excellent, although where closures of less than 0.2 mm are measured the comparison with calculations is limited by measurement reproducability. Once measurements commenced the averaged measured closures remain to within 30% of the calculated total closure in each drift. 9 figures, 1 table.
Research Organization:
Lawrence Livermore National Lab., CA (United States)
DOE Contract Number:
W-7405-ENG-48
OSTI ID:
59245
Report Number(s):
UCRL--87179; CONF-820803--6; ON: DE82013996
Country of Publication:
United States
Language:
English