Title: Jackpile-Paguate Uranium Mine Reclamation Project, Laguna Indian Reservation, Cibola County, New Mexico

Abstract

Approval of a reclamation plan is proposed for the Jackpile-Paguate uranium mine, located on three leases of Laguna Indian tribal lands in Cibola County, 40 miles west of Albuquerque, New Mexico. The mine was operated by Anaconda Minerals Company from 1953 through early 1982. Of the total 7868 leased acres, 2656 acres were disturbed by mining. The disturbed areas include 3 open pits, 32 waste dumps, 23 protore (subgrade ore) stockpiles, 4 topsoil stockpiles, and 66 acres of buildings and roads. Three alternative plans are under consideration, involving different filling treatments of the open pits. Under Anaconda's proposal, the open pits would be backfilled to at least three feet above projected ground water recovery levels. The DOI plan would involve backfilling the pits with protore, excess material from waste dump resloping, and soil cover the elevations 40 to 70 feet higher than Anaconda's minimum. The pits then would remain as closed basins, or open channels would be constructed to convey runoff from the pit areas to the Rio Paguate. The Laguna proposal would consist of backfilling the pits seven feet above the DOI proposal. For all alternatives, highwall stability techniques would involve removal of loose material and buttressing with wastemore » and overburden. Waste dump slopes would be reduced to between 2:1 and 3:1, and slopes could be terraced. Jackpile Sandstone exposed by resloping would be covered with four feet of overburden and one foot of topsoil. Mine site facilities would either be removed or cleaned up and left intact. All disturbed areas would be covered with topsoil and seeded. Reclamation would be considered complete when revegetated sites reached either 70% or 90% of that found on comparable reference sites. Post-reclamation monitoring periods would be 3, 5, or 10 years, depending on the alternative chosen. Cost estimates range from $54.2 million to $57.4 million.« less

Publication Date:
Research Org.:
Bureau of Land Management, Albuquerque, NM (USA)
OSTI Identifier:
5882296
Alternate Identifier(s):
OSTI ID: 5882296
Report Number(s):
EIS-85-0155(Draft); BLM-NM-ES-85-001-4134
Resource Type:
Technical Report
Resource Relation:
Other Information: EPA No. 850088D; DOI
Country of Publication:
United States
Language:
English
Subject:
29 ENERGY PLANNING, POLICY AND ECONOMY; 54 ENVIRONMENTAL SCIENCES; LAND RECLAMATION; ENVIRONMENTAL IMPACTS; ABANDONED SITES; ENVIRONMENTAL IMPACT STATEMENTS; INDIAN RESERVATIONS; NEW MEXICO; REVEGETATION; URANIUM MINES; DOCUMENT TYPES; FEDERAL REGION VI; MINES; NORTH AMERICA; UNDERGROUND FACILITIES; USA 530200* -- Environmental-Social Aspects of Energy Technologies-- Assessment of Energy Technologies-- (-1989); 290300 -- Energy Planning & Policy-- Environment, Health, & Safety; 510500 -- Environment, Terrestrial-- Site Resource & Use Studies-- (-1989)

Citation Formats

Not Available. Jackpile-Paguate Uranium Mine Reclamation Project, Laguna Indian Reservation, Cibola County, New Mexico. United States: N. p., 1985. Web.
Not Available. Jackpile-Paguate Uranium Mine Reclamation Project, Laguna Indian Reservation, Cibola County, New Mexico. United States.
Not Available. Fri . "Jackpile-Paguate Uranium Mine Reclamation Project, Laguna Indian Reservation, Cibola County, New Mexico". United States.
@article{osti_5882296,
title = {Jackpile-Paguate Uranium Mine Reclamation Project, Laguna Indian Reservation, Cibola County, New Mexico},
author = {Not Available},
abstractNote = {Approval of a reclamation plan is proposed for the Jackpile-Paguate uranium mine, located on three leases of Laguna Indian tribal lands in Cibola County, 40 miles west of Albuquerque, New Mexico. The mine was operated by Anaconda Minerals Company from 1953 through early 1982. Of the total 7868 leased acres, 2656 acres were disturbed by mining. The disturbed areas include 3 open pits, 32 waste dumps, 23 protore (subgrade ore) stockpiles, 4 topsoil stockpiles, and 66 acres of buildings and roads. Three alternative plans are under consideration, involving different filling treatments of the open pits. Under Anaconda's proposal, the open pits would be backfilled to at least three feet above projected ground water recovery levels. The DOI plan would involve backfilling the pits with protore, excess material from waste dump resloping, and soil cover the elevations 40 to 70 feet higher than Anaconda's minimum. The pits then would remain as closed basins, or open channels would be constructed to convey runoff from the pit areas to the Rio Paguate. The Laguna proposal would consist of backfilling the pits seven feet above the DOI proposal. For all alternatives, highwall stability techniques would involve removal of loose material and buttressing with waste and overburden. Waste dump slopes would be reduced to between 2:1 and 3:1, and slopes could be terraced. Jackpile Sandstone exposed by resloping would be covered with four feet of overburden and one foot of topsoil. Mine site facilities would either be removed or cleaned up and left intact. All disturbed areas would be covered with topsoil and seeded. Reclamation would be considered complete when revegetated sites reached either 70% or 90% of that found on comparable reference sites. Post-reclamation monitoring periods would be 3, 5, or 10 years, depending on the alternative chosen. Cost estimates range from $54.2 million to $57.4 million.},
doi = {},
journal = {},
number = ,
volume = ,
place = {United States},
year = {1985},
month = {2}
}

Technical Report:
Other availability
Please see Document Availability for additional information on obtaining the full-text document. Library patrons may search WorldCat to identify libraries that may hold this item. Keep in mind that many technical reports are not cataloged in WorldCat.

Save / Share: